Jackwell Pump at Jaykawadi starts; water reaches 4 km through 2500 mm main pipeline

By Lokmat Times Desk | Updated: March 23, 2026 22:20 IST

Lokmat News NetworkChhatrapati Sambhajinagar:Another major milestone in the new water supply scheme project was achieved on Monday. ...

Open in App

Lokmat News Network

Chhatrapati Sambhajinagar:

Another major milestone in the new water supply scheme project was achieved on Monday. A 3,700-horsepower pump at the jackwell constructed at Jaykawadi Dam was started at 8 pm, sending water into the massive 2,500 mm diametre pipeline. Water was successfully carried 4 km along the pipeline, cleaning and flushing it in the process. The pump test was conducted successfully in the presence of municipal commissioner G Sreekanth.

The new water project, being implemented at a cost of Rs 2,740 crore, is gradually completing its various key stages. The Maharashtra Jeevan Pradhikaran (MJP) and the municipal corporation are completing the final phases. The first phase is almost complete, and efforts are underway to bring an additional 200 MLD of water to the city. On Gudi Padwa, water from Jaykawadi Dam was siphoned into the jackwell, where it was held for three days.

No major leakage was detected in the jackwell. Following the successful preliminary test, pumping tests resumed on Monday morning. Mahavir Hydro, Flute Electromate, and GVPR jointly conducted the testing. Although testing was planned to start at 5 pm, minor technical issues caused a delay. The pump was finally started at 8 pm in the presence of municipal commissioner, along with MJP chief engineer Manisha Palande and GVPR general manager Mahendra Gogulothu.

Test successful

According to the civic chief and the MJP chief engineer, the 3,700-horsepower pump ran successfully for about one hour, shutting down at 9 pm. Water flowed through the 2,500 mm diametre pipeline, reaching a scour valve near the crematorium after 1 km, where excess water was released. The entire testing process was completed successfully.

Water reached 4 km

The pipeline from Jaykawadi Dam to Nakshatrawadi water treatment plant spans 38 km. Scour valves are placed every 4–5 km to release water and flush out impurities. This pipeline cleaning process is expected to continue for at least 8–10 days.

Open in App

Related Stories

InternationalIraq welcomes ceasefire announcement between US and Iran, calls for 'serious' dialogue

InternationalIran agrees to open Strait of Hormuz after Trump's 14-day ceasefire announcement

InternationalTrump pauses Iran strikes for two weeks

InternationalPakistan PM seeks pause on Trump's threats against Iran

InternationalIran's Supreme National Security Council claims "historic victory" after Trump suspends bombing campaign for 2-weeks

Aurangabad Realted Stories

AurangabadStorytelling contest in Bamu today

AurangabadTheatre arts carry power to challenge authority: Manjul Bharadwaj

AurangabadBITSAT- aspirants worried over clash of schedule with MHT- CET

AurangabadLPG rate at Rs 99.90 per litre from today

AurangabadGanori school selected for state’s first ‘AI Lab’