Will new water supply scheme be completed by March 31?

By Lokmat English Desk | Updated: February 5, 2025 19:55 IST

Lokmat News NetworkChhatrapati Sambhajinagar:The Maharashtra Jeevan Pradhikaran (MJP), Chhatrapati Sambhajinagar Municipal Corporation (CSMC) and the political leaders ...

Open in App

Lokmat News Network

Chhatrapati Sambhajinagar:

The Maharashtra Jeevan Pradhikaran (MJP), Chhatrapati Sambhajinagar Municipal Corporation (CSMC) and the political leaders have assured of supplying 200 MLD of water to the city, through the new 2500 mm diameter pipeline, by March 31. However, if we review the situation, it seems that it is a distant dream as in the coming 54 days, the works like laying of a 3-km length pipeline, construction of surge tanks at four spots near the main pipeline, and complete the first phase work of Jack Well in Jayakwadi Dam. Hence, it is apparent the citizens would continue to face shortage of water in summer like every year.

There are several obstructions at different places in the laying of the 2500 mm pipeline. They are yet to be overcome. Besides, if the Jack Well work gets completed, it would remain inoperative, as the pipeline work has not been completed. So the water could not be lifted and supplied ahead. Hence the announcement of March 31 is likely to remain as an announcement for the namesake.

New Chapter of Surge Tanks

The height of the water pipeline from Jayakwadi to Nakshatrwadi Hills is approximately 130 meters. If, in the future, the pipeline pumps fail or there is a sudden power outage, the water inside the pipeline will rush back toward Jayakwadi at an immense speed. These water surges could be extremely dangerous for the pipeline system.

To prevent such risks, a decision has been made to install four surge tanks at different locations. This has also been mentioned in the Bombay High Court's orders.

Four more tanks needed

Four more tanks with capacity varying from 50,000 litres to 3 lakh litres will be built near the main pipelines at Pimpalwadi Substation, near Irrigation Department Colony, Dhorkin and Allana Company. The municipal commissioner G Sreekanth held a meeting on Wednesday to acquire private land near Allana Company. The landowner has agreed to give away his land. Henceforth it would take time to acquire land take possession of the same and then start the construction.

900 mm work at a slow pace

A new water treatment plant is being built at Pharola. It will treat water lifted through a 900-mm pipeline. The work is going on at a snail’s pace. Hence it is impossible that the new scheme work will be completed by March 31. However, if the 900-mm pipeline project is completed then the city would get a quantity of 75 MLD of water. At least the citizens would be able to quench their thirst during the summer season.

Open in App

Related Stories

InternationalUSS Spruance forces Iranian cargo vessel to turn back amid ongoing naval blockade: US Central Command

NationalUnion Health Ministry hosts first BRICS health working group meeting 2026 in New Delhi

InternationalRepresentative of Iran's Supreme Leader in India calls West Asia conflict "individual war", says Israel sought conflict for 40 years

InternationalQatari Emir calls for de-escalation amid West Asia tensions in phone conversation with US President Trump

NationalWomen's Reservation Bill will bring "new dawn" in J&K: BJP MLA Shagun Parihar

Aurangabad Realted Stories

AurangabadStudents of city CBSE schools shine in 10th grade exam-I

Aurangabad15-yr-old moped rider killed in high-speed car collision

AurangabadDeadlock resolved after 6.5 hours; ZP subject committees elected unopposed

AurangabadCBSE Grade 10 Results Out: Toppers Share Success Stories

AurangabadYouth attacked with knife after asking to turn off DJ during celebrations