Mumbai-Ahmedabad Bullet Train project sees progress in track installation using Japanese J-slab system

By ANI | Updated: April 22, 2026 17:10 IST

Ahmedabad (Gujarat) [India], April 22 : Track installation work on the Mumbai-Ahmedabad Bullet Train project is progressing steadily, with ...

Open in App

Ahmedabad (Gujarat) [India], April 22 : Track installation work on the Mumbai-Ahmedabad Bullet Train project is progressing steadily, with the adoption of the advanced J-Slab ballastless track system based on the Japanese Shinkansen technology, which is being used for the first time in India, according to an official statement by the National High Speed Rail Corporation Limited (NHSRCL).

The NHSRCL stated that the J-Slab track system comprises four key componentsRC Track Bed, Cement Asphalt Mortar (CAM), Pre-cast Track Slab, and rails with fastenersdesigned to support high-speed train operations.

To support the production of track slabs, two state-of-the-art Track Slab Manufacturing Facilities (TSMF) have been set up at Kim near Surat and Anand in Gujarat. These facilities are producing high-grade concrete slabs with precise dimensions to ensure a consistent supply for the project.

The slabs are stored at the factory and transported via trailers to Track Construction Bases (TCBs), which act as operational hubs for handling materials, machinery, and equipment both on the ground and at the viaduct.

At present, ten TCBs are operationalfour between Surat, Bilimora and Vapi, and six between Vadodara, Anand and Ahmedabad.

National High Speed Rail Corporation Limited (NHSRCL) is a government-owned entity, specifically a "Special Purpose Vehicle" (SPV). It is a joint venture company involving the Central Government through the Ministry of Railways (50% equity) and the state governments of Gujarat (25%) and Maharashtra (25%).

According to the statement, significant progress has been made in track construction. A total of 185 route km of RC Track Bed has been laid, while 188 route km of track slabs have been manufactured. Additionally, track slabs have been laid and CAM injected across 70 route km.

The company also added that the track installation process is fully mechanised and uses specialised machinery designed as per Japanese construction practices, with most equipment manufactured in India.

Among the key machines being used is the Flash Butt Welding Machine (FBWM), which welds 25 m long 60 kg rails into 200 m long panels at the TCB. These welded rails undergo strict approval processes to ensure they are fit for high-speed operations at 320 kmph. Training and certification for rail welding and inspection have been conducted by the Japanese company JARTS.

The Track Slab Laying Car (SLC) is used to lift and place precast slabs onto the viaduct, with the capacity to handle five slabs at a time. Meanwhile, the Rail Feeder Car (RFC) is used to transport and lay 200 m long rail panels over the track bed.

After slab placement, the Cement Asphalt Mortar Injection Car (CAM Car) is deployed to inject the CAM mixture beneath the slabs, ensuring proper alignment and levelling of the track.

The adoption of advanced technology and mechanised processes is expected to enhance the efficiency and precision of track installation for India's first high-speed rail corridor.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

InternationalIndia and Germany sign Defence Industrial Roadmap during Rajnath Singh's Berlin visit

EntertainmentParineeti Chopra believes in being kind to yourself: Stop stressing over little things

BusinessIndia can grow above 7 pc even with crude at $90–100: Industry

NationalMultiple shutdowns paralyse life across Manipur's valley and hill districts

InternationalIndia, Japan launch inaugural AI dialogue to shape next decade

Business Realted Stories

BusinessFDI companies' paid-up capital hits Rs 5.96 lakh crore in 2024-25: RBI

BusinessBanks, financial institutions facilitating online money gaming to face penalties under new Act: MeitY Secretary

BusinessMPC members flag West Asia conflict; oil shock as key risks, back status quo on rates

BusinessNutrition advice should be individualised, not standardised: Minister

Business41 biogas cylinder filling and storage plants granted approval, license issued to 14 plants: Centre