Pakistan Auditor General report reveals financial irregularities of Rs 2.77 billion in Peshawar's BRT project

By ANI | Updated: December 7, 2020 11:50 IST

Pakistan's Auditor General report has revealed financial irregularities worth over Rs 2.77 billion in Peshawar's Bus Rapid Transport project.

Open in App

Pakistan's Auditor General report has revealed financial irregularities worth over Rs 2.77 billion in Peshawar's Bus Rapid Transport project.

SAMAA TV cited the AGP report as saying that the changes made to the design of the mega-project have increased its cost by Rs17 billion (from Rs 49 billion to Rs 66 billion).

The report has further highlighted that "unauthorised payments" of Rs 17.7 million were made to several officials including Khyber Pakhtunkhwa's additional chief secretary, from the Project Implementation Unit's fund, SAMAA TV said.

After the revelation, Ikhtiyar Wali, Pakist Muslim League (Nawaz) (PML-N) spokesperson from Khyber Pakhtunkhwa, has demanded the accused to be brought to justice and the BRT project be handled by a third party.

Meanwhile, Pakistan Tehreek-e-Insaf's provincial minister Shaukat Yousafzai has refuted the report of any corruption in the BRT project.

This comes weeks after Pakistan's high-quality bus-based transit system came under the line of fire when one of its buses broke down on the main corridor near the Abdara station leading to the social media users questioning the country's bus-based transit system and the Imran Khan-led administration.

Earlier this year, the BRT project in Peshawar city faced criticism by the people after the stations got flooded and witnessed water leakages during heavy rains.

Several videos went viral on social media showing water leakages at the stations.

The BRT project has been constructed by a consortium led by China Railway 21st Bureau Group and it has witnessed several accidents since its inauguration on August 13.

The project, built at a cost of Rs 70 billion is a 27.5 kilometre-long corridor track with 31 stations and seven feeder routes stretching 62km with 146 stops to facilitate thousands of passengers every day.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

NationalPolice attach Rs 1.20 crore property of drug peddler in J&K's Udhampur

NationalBengal: Man stabbed to death in Kolkata’s Rajabazar area

BusinessWith 5519 Patents and 20,000+ Research Publications Chandigarh University ranks amongst India's Top Research - Intensive Universities

BusinessJerai Fitness Rings in the New Year with Buyback Offer for gym equipment to help Gyms upgrade in CY2026

BusinessEmpowerHER25 Brings Together 300+ Women Entrepreneurs in Pune to Discuss Scalable, Tech-Enabled Business Growth

International Realted Stories

InternationalASEAN Foreign Ministers urge Cambodia and Thailand to cease hostilities

InternationalNearly 4,000 Afghan refugees deported from Iran, Pakistan in single day

InternationalASEAN, Cambodia discuss peaceful settlement of disputes through dialogue

InternationalBangladesh burns: Another student leader faces murderous attack

InternationalBangladesh minorities protest 'persecution, silence' under Yunus-led interim rule