PoGB: Investigation reveals major flaws in Bale Gowand hydropower project

By ANI | Updated: February 9, 2025 23:45 IST

Gilgit [PoGB], February 9 : A recent investigation into the 2 MW Bale Gowand Hydropower Project on the Hoshe ...

Open in App

Gilgit [PoGB], February 9 : A recent investigation into the 2 MW Bale Gowand Hydropower Project on the Hoshe River in Pakistan-occupied Gilgit Baltistan, has revealed major issues with its construction and planning, according to a report by Pamir Times.

Initiated under the 2012 Annual Development Program (ADP) at a cost of Pakistani Rupees (PKR) 395.324 million, the project began construction in 2014 and was completed in 2022. However, just two months after completion, cracks appeared in the power channel and four bays, leading to water leakage and a drop in power generation, Pamir Times reported.

A three-member committee, formed under the chairmanship of Engineer Zia-ur-Rehman, visited the site and submitted a detailed report, as reported by Pamir Times.

The investigation revealed that the four bays, which store and direct water to the turbines, were built on soft and unstable ground. This resulted in cracks due to subsidence. Similarly, the spillway was constructed on poor-quality land, contributing to further damage, while the 4,300-foot-long power channel was found leaking water due to cracks in its walls. The report attributes these issues to the use of substandard materials, including a poor cement-water ratio, Pamir Times reported.

Additionally, the feeder channel, relocated 700 feet after the 2015 floods, faces similar instability and water pressure issues. The report suggests urgent repairs and improvements, including rebuilding the four bays on more stable terrain and relocating the spillway to a better-suited location, as reported by Pamir Times.

According to Pamir Times, the investigation also criticizes the contractors, Ahmed Ali and Sons and Ghulam Mehdi and Sons, for their subpar work. Despite the potential for increasing the project's capacity to 6 MW, the report urges authorities to focus on repairing the existing infrastructure instead of expanding power generation.

The report highlights the urgent need for corrective measures to prevent further damage and ensure the project's long-term sustainability. It also calls for a thorough review of the design and construction processes, recommending stricter quality control in future projects to avoid similar failures.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

CricketBrisbane Heat Women vs Melbourne Renegades Women LIVE Cricket Streaming: When and Where to Watch WBBL Match in India

InternationalLebanon's normalization with Israel impossible: Parliament speaker Berri

InternationalHouthis arrest Yemeni nationals accused of spying for Israel

NationalVice President Radhakrishnan to visit Karnataka today

NationalBihar polls 2025: Campaigning to end for second phase, voting on Nov 11 for 122 seats

International Realted Stories

InternationalTaiwan records 10 sorties of PLA aircraft, 10 PLAN vessels operating around its territory

InternationalNepal: Flight operations resume at Tribhuvan International Airport

InternationalEgypt announces new gas discovery in Western Desert

International11th edition of Indo-Sri Lanka 'Exercise Mitra Shakti' to take place in Belagavi

InternationalTwo more terrorists related to Hezbollah neutralised by IDF