City
Epaper

After CM's green flag, Mumbai Metro train trials to start early 2022

By IANS | Updated: October 1, 2021 19:35 IST

Mumbai, Oct 1 A day after Maharashtra Chief Minister Uddhav Thackeray gave the go ahead, the Mumbai Metro ...

Open in App

Mumbai, Oct 1 A day after Maharashtra Chief Minister Uddhav Thackeray gave the go ahead, the Mumbai Metro Rail Corporation Ltd (MMRCL) on Friday said it plans to start trial runs for the Mumbai Metro 3 line by early 2022.

The state government has permitted the MMRCL to create a temporary facility - a train delivery and testing track area for the technical trials of the prototype 8-coach trains due to arrive here by December, said MMRCL Managing Director Ranjit Singh Deol.

After a two-week period to assemble the train coaches, by January 2022, the trials for the Colaba-Bandra-SEEPZ fully-underground Mumbai Metro 3 corridors shall start, he added.

The trials will be conducted from the mouth of a ramp on the west of the Marol-Maroshi Road in Andheri east, in an area vacated by diversion of the road to an upcoming underpass.

The ramp - which connects the underground part of the Metro line with the surface - coming up here is around 225 metres long.

Presently, two metro trains of 8-cars each are ready, a third is being manufactured and for the testing programme of the prototype train, the parking will be at at the temporary facility at Marol-Maroshi Road, said Deol.

The development comes amid apprehensions that a Centre-State tug-of-war for the car-shed depot may delay the project by two years while an alternative site is being acquired for the prestigious Mumbai Metro Line 3.

Thackeray has also directed the MMRCL not to chop a single tree in the Aarey Colony area - which was rejected as the original proposed site for the car-shed - and instead build the ramp in Marol-Maroshi Road for conducting the train trials.

The manufacturer, Alstom, has already conducted technical trials of the 8-car trains in SriCity, Andhra Pradesh, and now the trains will be coming to Mumbai for rigorous trials of 10,000-kms before the Mumbai Metro 3 operations begin with 31 trains.

Currently, 97 per cent of the tunnel work and around 70 per cent of the civil works for the Line 3 is ready and the technical trials of the prototype train would mark a major milestone, said Deol.

Incidentally, through a NITI Aayog delegation which visited the state recently, Thackeray again appealed to Prime Minister Narendra Modi to intervene and end the tussle of the Kanjurmarg site selected for the Mumbai Metro carshed, which is stuck in a legal dispute.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Ranjit singh deolUddhav ThackerayMumbai MetroMumbai Metro Rail Corporation LtdUddhav fadnavisMaharashtra congress working
Open in App

Related Stories

MumbaiMumbai Metro Timetable Updated Ahead of Lines 9 & 2B Rollout; Check Timings and New Schedule Here

MumbaiMumbai Mega Infra Launch: CM Devendra Fadnavis to Inaugurate Metro Lines 9, 2B, Twin Tunnel and Pod Taxi Today

MumbaiMumbai Metro Line 3 News: Churchgate Station Gate Closed Temporarily, Reopening on April 6

MaharashtraSunetra Pawar Reaches Out to Uddhav Thackeray for Support Ahead of Baramati Bypoll

MumbaiMumbai Metro Line 2B Phase 1 to Open on April 3, Boosting Chembur-Mankhurd Connectivity

Maharashtra Realted Stories

MumbaiMumbai Weather Update: Temperature Likely To Be 32 Degrees in City; AQI in 'Good' Category

MumbaiMumbai: Maharashtra Government Orders Marathi Test, Licence Check for Auto, Taxi Drivers in Mira-Bhayandar

MaharashtraAmravati Accident: 4 Dead, 3 Injured as Car Loses Control and Hits Tree Near Belora Airport

MumbaiMumbai Businessman Duped of ₹18 Lakh on Pretext of Cryptocurrency Trading; Three Arrested

MumbaiMumbai ANC Seizes 7.6 Kg Hydroponic Cannabis Worth Rs 7.69 Crore in Vile Parle; One Drug Peddler Arrested