BMC to complete first phase of Mumbai coastal road by November 2023

By Lokmat English Desk | Updated: February 25, 2023 08:16 IST

The Brihanmumbai Municipal Corporation’s (BMC), which is executing the Mumbai coastal road project, has just 170 metres left to ...

Open in App

The Brihanmumbai Municipal Corporation’s (BMC), which is executing the Mumbai coastal road project, has just 170 metres left to excavate in the second tunnel, and the daylighting is expected to be completed by mid-March. Mantayya Swami, chief engineer of the project, said that the civic body had plans to open the road by November.

The bridge connecting the Worli-Chowpatty stretch was left midway owing to objections from fishermen who wanted a bigger span on the last leg. “We are constructing a sample promenade now,” said deputy engineer Vijay Zore. “The Marine Drive promenade is 3.25 km long and 10 metres wide while the coastal road promenade is 7.5 km long and 20 metres wide.”

Zore said that people could enter the promenade via the pedestrian underpass. “We have four giant car parks under the coastal road, which can accommodate 1,800 cars,” he said. “There is also a cycling track, which will be on the landward side. We will also have an open area of 70 hectares, of which 50 hectares will be green space.” The project is being funded by the BMC, and has cost the civic body ₹8,249 crore. 

Initially seeded during the Congress-NCP regime under the then chief minister Prithviraj Chavan, it was conceptualized as a road on stilts. The design was later changed.Shiv Sena (UBT) chief Uddhav Thackeray was keen that the no-toll road be built by the BMC and wanted to flaunt it as the Sena-ruled civic body’s achievement. During the BJP-Shiv Sena government tenure, the then chief minister Devendra Fadnavis got most of the permissions needed for the project. The project was launched by the BMC in December 2018 in the presence of Thackeray. The present CM Eknath Shinde is eager to inaugurate the coastal road during his tenure and has told the BMC to complete it by December 2023. Shinde has also asked MMRDA to speed up the construction of the Worli-Sewri connector to connect the project to the trans-harbour link.

Tags: Brihanmumbai Municipal CorporationMumbai coastal road projectMumbai News
Open in App

Related Stories

MaharashtraVoters Back Development, Not Political Brands’: Eknath Shinde Targets Uddhav-Raj as BMC 2026 Polls Heat Up

MumbaiSuspicious Bag Outside Nitesh Rane’s Mumbai Residence Triggers Security Alert

MumbaiBMC Election 2026: Mahayuti Unveils Manifesto Promising Slum-Free Mumbai, Interest-Free Loans for Women

MumbaiDharavi Redevelopment: Devendra Fadnavis to Request PM Narendra Modi to Launch Project, Assures 350 Sq Ft Homes

MumbaiMumbai Police Hop on ‘Bhagwanji in Car’ Viral Trend, Netizens Cheer

Maharashtra Realted Stories

Navi MumbaiPanvel Municipal Election 2026: Heat Rises as Public Questions Vanishing Civic Concerns

MaharashtraNanded Municipal Election 2026: BJP Sees Uneven MLA Participation as Two Stay Away

PunePune Crime News: Three Held Within 24 Hours for Armed Robbery Attempt in Kalyaninagar Flat

MaharashtraRatnagiri: Saree-Clad Women Take to Football Field, Send Strong Message on Empowerment (Watch Video)

MaharashtraKolhapur ACB DYSP Vaishnavi Patil Injured in Major Car Accident Near Chitradurga