BMC to complete first phase of Mumbai coastal road by November 2023

By Lokmat English Desk | Updated: February 25, 2023 08:16 IST

The Brihanmumbai Municipal Corporation’s (BMC), which is executing the Mumbai coastal road project, has just 170 metres left to ...

Open in App

The Brihanmumbai Municipal Corporation’s (BMC), which is executing the Mumbai coastal road project, has just 170 metres left to excavate in the second tunnel, and the daylighting is expected to be completed by mid-March. Mantayya Swami, chief engineer of the project, said that the civic body had plans to open the road by November.

The bridge connecting the Worli-Chowpatty stretch was left midway owing to objections from fishermen who wanted a bigger span on the last leg. “We are constructing a sample promenade now,” said deputy engineer Vijay Zore. “The Marine Drive promenade is 3.25 km long and 10 metres wide while the coastal road promenade is 7.5 km long and 20 metres wide.”

Zore said that people could enter the promenade via the pedestrian underpass. “We have four giant car parks under the coastal road, which can accommodate 1,800 cars,” he said. “There is also a cycling track, which will be on the landward side. We will also have an open area of 70 hectares, of which 50 hectares will be green space.” The project is being funded by the BMC, and has cost the civic body ₹8,249 crore. 

Initially seeded during the Congress-NCP regime under the then chief minister Prithviraj Chavan, it was conceptualized as a road on stilts. The design was later changed.Shiv Sena (UBT) chief Uddhav Thackeray was keen that the no-toll road be built by the BMC and wanted to flaunt it as the Sena-ruled civic body’s achievement. During the BJP-Shiv Sena government tenure, the then chief minister Devendra Fadnavis got most of the permissions needed for the project. The project was launched by the BMC in December 2018 in the presence of Thackeray. The present CM Eknath Shinde is eager to inaugurate the coastal road during his tenure and has told the BMC to complete it by December 2023. Shinde has also asked MMRDA to speed up the construction of the Worli-Sewri connector to connect the project to the trans-harbour link.

Tags: Brihanmumbai Municipal CorporationMumbai coastal road projectMumbai News
Open in App

Related Stories

MumbaiMira Road Crash: Car Loses Control, Slams Divider Near Silver Park at 3 AM (Watch Video)

MumbaiMumbai Crime: 27 LPG Cylinders Stolen from Kandivali Tempo, Accused Arrested

MumbaiMumbai Viral Video: Commuters Sit on Railings Between Tracks to Catch Train Amid Rush

MumbaiMumbai Auto Rickshaw Protest: Unions Slam ₹800 Welfare Board Registration Fee at Andheri RTO

EntertainmentSamay Raina Shares Surprise Fan Encounter at Police Station during India’s Got Latent Row (Watch Video)

Maharashtra Realted Stories

PunePimpri: Open DP Boxes Used for Illegal Power Supply Near MSEDCL Office

MaharashtraMPSC Results 2024: Solapur’s Vijay Lamkane Ranks First in State, Aarti Jadhav Tops Among Women

PunePune Horror: Pregnant Woman Assaulted by In-Laws Over Money; Case Registered Against Four

ThaneThane Road Accident: Two Killed, One Injured as Trio on Two-Wheeler Hit by Bus in Mumbra

MaharashtraST Bus Fare Hike: MSRTC To Increase Bus Ticket Prices From April 15; Check Location Wise Rates