Contractor builds same road twice for NMC, NIT

By Lokmat English Desk | Updated: September 18, 2023 14:37 IST

NIT builds it in Oct 2022 while NMC in March 2023

Open in App

Harsh Yadav (Nagpur)

Irregularities are nothing new in Nagpur Municipal Corporation (NMC) and Nagpur Improvement Trust (NIT) but this case must take the pride of place among all such aberrancies.

NIT asked a contractor M/s. Hitesh Construction run by Prakash Potpuse to build a tar road and storm water drain in Tulsi Nagar, Bhandewadi in October 2022. Five months later, NMC's slum department asked the same contractor to build a concrete road and storm water drain at the same place. The contractor calmly executed the works, pocketing a total of about Rs 4.95 crore in the two contracts. Maharashtra Navnirman Sena (MNS) leader Upesh Utkhede has alleged a major scam in these works. Lokmat Times has copies of stinky documents which are indicative of something fishy.

NIT's superintending engineer on October 12, 2022 had issued a work order to M/s. Hitesh Construction for building a tar road and storm water drain in Tulsi Nagar. The cost of work was Rs 2.60 crore. Then on March 9, 2023, NMC's slum department issued a work order to concretize the same road and build a storm water drain. This work was also awarded to M/s. Hitesh Construction of Potpuse. The cost of this work was Rs 2.35 crore. The bills of both works have readily been already cleared by both NMC and NIT.

MNS' East Nagpur constituency president Upesh Utkhede alleged that NMC had committed a scam by asking the same contractor to concrete the road, which was built five months ago. Moreover, storm water drains were built twice. "This is a clear example of corruption by municipal officers and contractors. The municipal commissioner should conduct a high level inquiry into this matter," he said.

When contacted, NMC's executive engineer (slum) Kamlesh Chavan, who had issued the work order, said that he could not say anything offhand and asked Lokmat Times to come to his office on Monday.

However, the contractor Prakash Potpuse offered an unconvincing explanation in this regard. He admitted that he had built a tar road first and then dug it up after five months. He then concretized it. Potpuse had no explanation for building storm water drains twice. Perhaps it was necessary and the public money being spent was not really going down the proverbial drain, but the stink still persists. Spending money on tarring a road and then digging it up to concretize it, doesn't really gel! The city fathers' new found love for concretized road works strikes a discordant note in this case.

Tags: Maharashtra NewsNagpur municipal corporation
Open in App

Related Stories

PunePune: Blaze Erupts in Meter Room at Municipal Employee Colony, Ambil Odha (Watch Video)

MaharashtraNalasopara: Police Seize MD Worth ₹1.14 Lakh, Arrest Two After High-Speed Chase

MaharashtraMaharashtra Accident: Car Catches Fire After Head-On Crash with Luxury Bus on Nagar-Manmad Highway; 1 Dead

MaharashtraMaharashtra: 34-Year-Old Found Dead Under Suspicious Circumstances in Khandnal Village

MaharashtraNaigaon Theft Case: Woman Nabbed With Stolen Property Worth ₹6 Lakh While Trying to Flee

Maharashtra Realted Stories

MaharashtraMaharashtra: Bike Thief Dies in Head-On Collision While Fleeing; Two Others Seriously Injured

ThaneThane: Police Nab 36-Year-Old in Dombivli for Possessing Pistols, Cartridges & Weapons

MaharashtraNagpur: Police Bust Sex Racket at Hotel on Umred Road, Seize Cash, Mobile, CCTV DVR

MumbaiMumbai Tragedy: Two Workers Killed, Three Injured as Excavated Soil Collapses at Construction Site

MaharashtraMaharashtra Tragedy: 12-Year-Old Vasai Student Dies After Being Forced to Do 100 Squats as Punishment