MMRDA’s Infrastructure Push: 60% Work Completed on Sewri-Worli Connector, Elphinstone ROB Next in Line

By Lokmat English Desk | Updated: March 24, 2025 18:44 IST

The Mumbai Metropolitan Region Development Authority (MMRDA) is all set to begin the reconstruction work of 100-year-old Elphinstone Road ...

Open in App

The Mumbai Metropolitan Region Development Authority (MMRDA) is all set to begin the reconstruction work of 100-year-old Elphinstone Road Over Bridge (ROB) under the Sewri-Worli Connector project. The reconstruction work is likely to begin by April second week the officials said, reported Mid-Day.

The officials said that all the technical and safety protocols have been followed and MMRDA is in the final stages of getting clearance from Mumbai Traffic Police. They expect that Mumbai Police will give a green signal to them for this project by April 10.

The officials said that demolition of this old ROB is quite a time-sensitive task and should be done before monsoon season hits the city, reported Mid-Day.

Also Read: Wild Encounter: Crocodile from Powai Lake Enters IIT Bombay (Watch Video)

Once the work begins on April 10, it will mark a major milestone in the project leading way for a modern double-decker structure. This double-decker structure is expected to improve East-West connectivity in Mumbai.

The Sewri-Worli Elevated Connector is 4.5 km long. It is a 4-lane (2+2) divided elevated corridor. This route will serve as a traffic dispersal route for the Mumbai section of Atal Setu. This will also connect Atal Setu to Bandra Worli Sea Link, and Mumbai Coastal Road. It will reduce travel time and provide a signal-free route for commuters travelling between Navi Mumbai and South & Central Mumbai.

This project includes the construction cost of two ROBs, one across the Harbour Line at Sewri and Another across the Central and Western Lines at Prabhadevi (Elphinstone Road). The Elphinstine Road ROB which will soon be demolished, is 13 meters wide and will be replaced with a double-decker bridge designed to handle huge traffic snarls.

Overall 60% work of the Sewri-Worli Connector project has been completed.

Tags: Sewri-worli elevated corridorMumbai NewsMaharashtra NewsInfrastructure development corporationMmrda
Open in App

Related Stories

MaharashtraMaharashtra: Over 300 Schools, 400 Junior College Divisions Declared Permanently Ineligible for Salary Grants

MaharashtraNagpur: Body of Unidentified Man Recovered from Futala Lake, Police Launch Investigation

MumbaiMumbai Police Trace Over 1,500 Missing and Stolen Mobile Phones, Hand Them Back to Owners

MumbaiMumbai: Speeding Car Kills 65-Year-Old in Matunga, Damages Multiple Vehicles

Navi MumbaiNavi Mumbai: Elderly Man Duped of Rs 1.54 Crore in ‘Digital Arrest’ Fraud in Panvel, Probe On

Mumbai Realted Stories

MumbaiMumbai: Customer Bites Vendor’s Fingers During Bill Dispute Over Samosa in Malad

MumbaiMumbai Local Train Update: Special Night Block on Western and Central Lines for Prabhadevi Bridge Demolition

MumbaiMumbai Local Train Mega Block on April 5, 2026: No Day Block on Western Line This Sunday; Check Details of Central and Harbour Lines

MumbaiMalad: Man Allegedly Bites Samosa Vendor’s Fingers Over Food Bill; Accused Arrested

MumbaiVasai-Virar Water Cut: Week-Long Supply Disruption From Today; Check Dates and Areas