Mumbai: Carnac Bridge Reconstruction Nears Completion, Set to Open by June 2025

By Amit Srivastava | Updated: January 31, 2025 19:42 IST

Mumbai: The Carnac Bridge, which will improve connectivity near South Mumbai, is expected to open for public use by ...

Open in App

Mumbai: The Carnac Bridge, which will improve connectivity near South Mumbai, is expected to open for public use by June 2025, according to the Brihanmumbai Municipal Corporation (BMC). A major milestone in the reconstruction of the Carnac Railway Flyover has been achieved with successfully launching a 550-metric-ton iron girder over the railway tracks near Masjid Bunder station.

The project, which connects P. D’Mello Road, is a crucial infrastructure development for South Mumbai’s traffic network.

The Central Railway administration, in coordination with the Brihanmumbai Municipal Corporation (BMC), executed this challenging task during a special railway and power block from 1:30 AM to 4:00 AM on January 31, 2025.

Technical Challenges Overcome

The girder installation faced delays on January 26, 2025, when only 12 meters remained to be launched due to unforeseen technical difficulties. However, after close coordination between BMC and Central Railway, the issues were resolved, and the remaining work was successfully completed.

The technically complex operation was carried out under the guidance of RITES Ltd, a premier engineering consultancy. The BMC’s Bridge Department, under the leadership of Commissioner Bhushan Gagrani, worked in close collaboration with Central Railway officials to ensure smooth execution.

Next Steps and Expected Completion

With the girder now in place, the next phase of work will focus on:

*Final installation of the iron girder

*Construction of pier foundations for approach roads

*Concrete work and load testing

According to BMC officials, the Carnac Bridge is expected to be open for traffic by June 2025. To avoid further delays, additional infrastructure work, such as anti-crash barrier installation and streetlight setup, will be carried out alongside ongoing construction.

Significance of the Carnac Flyover

The Carnac Bridge plays a key role in managing traffic flow between Chhatrapati Shivaji Maharaj Terminus (CSMT), Masjid Bunder, and Mohammad Ali Road. The original Carnac Bridge on Lokmanya Tilak Road was declared unsafe, prompting the BMC to undertake its reconstruction.

The first phase of the girder movement took place on January 14, 2025, when the 550-metric-ton iron structure was shifted 9.30 meters within BMC limits. On January 25-26, 2025, the girder was moved 58 meters, but the final 12 meters remained due to technical issues. These were successfully resolved, and the girder launching was completed on January 31, 2025.

Tags: Carnac BridgeCarnac Bridge demolitionBrihan mumbai municipal corporationSouth MumbaiMasjid bunderP Dmello RoadCentral Railway
Open in App

Related Stories

MumbaiMumbai: Central Railway Launches QR Code-Based Timetable System for Mail/Express Trains

MumbaiMumbai: BMC to Complete Road Concretization by May 31

MumbaiMumbai Local Train Update: Central Railway Announces Power Blocks on Kalyan-Karjat Line Between April 29 to May 5

MumbaiMumbai Local Train News: Central Railway Reconsiders AC Services for Harbour Line After Rising Demand on Main Line

Navi MumbaiCarnac Bridge to Reopen by June 10; BMC Sets 53-Day Completion Deadline

Mumbai Realted Stories

MaharashtraMaharashtra CM Devendra Fadnavis’s Daughter Secures 92.6% in ICSE 10th Board Exams

MumbaiMumbai: FIR Registered in Vakola Hit-and-Run Case That Killed Pedestrian After 8-Month Delay

MumbaiDeven Bharti Takes Charge as Mumbai Police Commissioner; Post Returns to ADG Rank After 10 Years

LifestyleHappy Maharashtra Day 2025 Wishes: Messages, Quotes, WhatsApp Status and Images to share and Celebrate Maharashtra Din

MumbaiMumbai: Gold Sales Cross ₹12,000 Crores Nationwide on Akshaya Tritiya; Mumbai MMR Sees ₹800 Crores Trade