Mumbai: Homeowners Claim Long-Awaited Dwellings After 50 Years in Transit Camp

By Lokmat English Desk | Updated: January 9, 2024 12:35 IST

Mumbai: After a 50-year wait, residents of the Durga Devi Cooperative Housing Society in Sion finally received their rightful homes. ...

Open in App

Mumbai: After a 50-year wait, residents of the Durga Devi Cooperative Housing Society in Sion finally received their rightful homes. 16 of the 36 residents were handed keys to their apartments during a ceremony on Sunday, tears of joy welling up in many eyes.

Last year, 'Lokmat newspaper highlighted the plight of these residents, prompting Legislative Assembly Speaker Rahul Narwekar to intervene and urge the government to expedite the process. Deputy Chief Minister Devendra Fadnavis also assured prompt action to reunite the residents with their homes. The then regional chief Pandurang Sakpal aided in arranging a meeting between the residents and MHADA in former MHADA chief Vinod Ghosalkar's office. The residents could not get possession due to technical issues in their papers. 

Later on, Santosh Shinde, the then regional chief of the Girgaon section met with MP Arvind Sawant regarding the issue. Following these interventions, a meeting was convened under the chairmanship of MHADA Vice President Sanjeev Jayswal. He instructed officials to complete the formalities and hand over the dwellings to the rightful owners.

Sunday's ceremony saw the participation of MP Arvind Sawant, MHADA officials including Joint Commissioner Umesh Wagh and Deputy Commissioner Virag Madavi, and property manager Avdhoot Belnekark, Vishal Birajdar, Umesh Mali and Balasaheb Patil. 

"We met MHADA officials and representatives countless times, hoping for our new homes," said Ganesh Shinde, secretary of the Durga Devi Cooperative Housing Society. "Technical issues and other hurdles stalled the process, but 'Lokmat' raised our voice and helped us secure justice."

With Legislative Assembly Speaker Narwekar taking the initiative and 'Lokmat' persistently pursuing the issue, the 50-year-old saga of delayed rehabilitation finally reached a happy conclusion.

Timeline of Events

  • 1974: The building was declared unsafe and evacuated for demolition.
  • 2008: MHADA awarded the reconstruction contract to Satish Construction through a tender process.
  • More than 15 years have passed since the reconstruction began.
  • Faulty construction due to MHADA's negligence.
  • The building's entrance was built only 5.5 feet wide.
  • 2018: MHADA conducted a lottery for 39 residents when Vinod Ghosalkar was the chairman.
  • 2019: Original documents were submitted to MHADA, and allotment letters were issued to residents.
Tags: MhadaSionMHADA HomesArvind SawantVinod Ghosalkar
Open in App

Related Stories

MumbaiMumbai: MHADA Launches Awareness Campaign for Redevelopment of 13,091 Dangerous Buildings

Mumbai‘Book My Home’: MHADA Launches New Digital Portal for Sale of 13,395 Unsold Flats

MaharashtraMHADA Konkan Board to Sell 13,395 Unsold Flats Under First-Come-First-Serve Scheme; Applicants Can Now Choose Flats Online

MumbaiMumbai: MHADA Announces Lottery for 5,000 Houses Ahead of Diwali 2025

MumbaiRajiv Gandhi Nagar Zopu Yojana: MHADA Launches Largest Slum Rehab Project in Malad, Covering 14,000 Huts

Mumbai Realted Stories

MumbaiMumbai Drug Bust: Narcotics Worth Rs 5.80 Crore Seized, Three Arrested

MumbaiCOVID-19 Relief Scam: EOW Files Chargesheet in Rs 14.57 Crore Khichdi Case

MumbaiMumbai Tragedy: Two Youths Die in Motorcycle Crash with Parked Tempo in Vile Parle; Driver Booked for Negligence

MumbaiMumbai: Bombay High Court Ruling Brings GST Relief to Redevelopment Homeowners

MumbaiMTNL Cable Theft Ring Exposed: Two Held in Multi-Crore Heist in Mumbai