Northern Section Of Barfiwala Bridge in Andheri To Open by June End

By Amit Srivastava | Updated: May 27, 2024 19:24 IST

The northern part of the Barfiwala Bridge in Andheri is set to open for traffic by the end of ...

Open in App

The northern part of the Barfiwala Bridge in Andheri is set to open for traffic by the end of June as its alignment with the Gopal Krishna Gokhale Bridge nears completion. According to a senior official from the Brihanmumbai Municipal Corporation (BMC), the remaining work involves casting and curating.The disparity between the Gopal Krishna Gokhale Bridge and Barfiwala Bridge, previously around 1,300 mm, has been significantly reduced to just 100 mm as of last week. "We anticipate completing the remaining alignment and proceeding with the casting work," stated Abhijit Bangar, additional commissioner of projects.

The anticipated completion date for the entire bridge has been extended to Nov. 15. "The contractor has been granted an extension of five and a half months, with a penalty of Rs 3 crore imposed for the delay," added Bangar, emphasizing that the entire bridge will be open for traffic by March 31, 2025.Earlier, the northern section of the Gopal Krishna Gokhale Bridge was opened for traffic on Feb. 26. The launching of girders for the second phase of the bridge was scheduled for completion by May 31. However, delays in the arrival of girder components from Ambala, Haryana, have occurred. Consequently, civic authorities have issued a notice to the contractor seeking clarification regarding the delay.

As per a senior civic official, the girder launching and overall completion of work, including surfacing the railway portion on the southern segment of Andheri's Gopal Krishna Gokhale Bridge, have been postponed to Nov. 15."We have approved a delay of 107 days, which was deemed justifiable. However, the contractor will face penalties for the unjustified delay of 59 days, as per the tender document conditions," explained Bangar. The closure of the Gokhale Bridge since November 2022 due to safety concerns has inconvenienced commuters in Andheri. Even with the opening of the northern segment after 15 months, commuters still faced challenges due to the height disparity of nearly two meters between the Gokhale and CD Barfiwala flyover. The BMC has undertaken alignment work after consulting Veermata Jijabai Technological Institute and the Indian Institute of Technology, with completion expected next month.

 

 

 

 

Tags: Barfiwala BridgeMumbai NewsMaharashtra NewsAndheri
Open in App

Related Stories

MumbaiMumbai: 3 Schoolgirls Molested by School Van Driver; Accused Arrested by Juhu Police

MumbaiMumbai Crime: Businessman Robbed in Lokhandwala After Offering Lift to Unknown Woman

PunePune Crime: 5 Assailants Kill Youth With Koyta in Broad Daylight Near Sinhgad College, Smash Head With Stone

PunePune Traffic News: Major Relief for Viman Nagar as One-Way Layout Finally Implemented

MumbaiMumbai: Ghatkopar School Children Suffer Suspected Food Poisoning After Eating Canteen Samosas

Mumbai Realted Stories

NashikNashik: Leopard Spotted Near Bhonsala Military School and College; Drones Deployed in Search Operation

MaharashtraDevendra Fadnavis Warns Congress of More Defeats Over Baseless ‘Vote Theft’ Claims

MumbaiUddhav Thackeray and Family Pay Respects to Shiv Sena Founder Bal Thackeray on His 13th Death Anniversary

ThaneThane: Chemical Truck Crashes Into Tree Near Crossing, Damages Autorickshaw and Streetlight

MumbaiTaxi, Auto Services to Be Impacted as CNG Supply Hit in Mumbai, Navi Mumbai and Thane; Check Reason