Delhi L-G gives nod for land acquisition for Barapullah corridor

By IANS | Updated: November 18, 2023 19:40 IST

New Delhi, Nov 18 Delhi L-G V. K Saxena on Saturday gave nod for acquisition of two small ...

Open in App

New Delhi, Nov 18 Delhi L-G V. K Saxena on Saturday gave nod for acquisition of two small parcels of land that will remove the final hurdle in completion of the critical Barapullah Corridor Phase-III project in the national capital, Raj Bhavan said.

The officials said that the L-G has asked the Chief Secretary to inquire into the “erred planning” and “assessment of land requirement” that essentially led to delaying of the project by six years and cost escalation by a whopping Rs 362 crore.

The L-G also directed for suspension of the engineers in-charge of the project right from the time of start of construction works on the project, if yet serving, and initiating suitable action against those who have retired, the official said.

The two land parcels measuring 1169.093 sqm and 709.901 sqm respectively are located in village Nangli Razapur, in South East District.

The Raj Bhavan officials, the project was held up due to non-acquisition of these land parcels all these years. The official said that while invoking the AAP government's oft-repeated claims that it was saving huge amount of public money by executing PWD projects before time and below the tendered amount,

The L-G noted that contrary to the claims made by even the Chief Minister (Arvind Kejriwal), the government will end up paying Rs 1,326.37 crore for the Barapullah Project Against the tender amount of Rs 964.00 crore.

“This amounts to an additional Rs 362.37 crore being paid to the contractor out of the government exchequer, while also delaying the project by over six years,” the official said.

The official said that Saxena has noted that there was “sheer negligence” on the part of the officers in respect of planning, inspection and field survey of land for the project resulting in delays of more than 06 years, apart from cost overruns running into hundreds of crore.

The L-G has also directed the Chief Secretary to prepare suitable SoP for lapse-free planning and timely execution of the projects of public importance including identification of land and assessing requisite area for acquisition of land, the official added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

International"We want Israel to get them fed," says Trump on Gaza

Other SportsFakhar Zaman ruled out of West Indies tour with hamstring injury

Cricket"It just felt like a wicket could fall with every ball": Sanjay Bangar reflects on 3rd session of Day 4 in series decider between India-England

MumbaiMumbai Building Collapse: Old Building Housing Post Office Collapses in Madanpura; Watch

NationalTelangana Congress MLA finds fault with CM’s remarks on social media journalists

National Realted Stories

NationalMamata inciting linguistic conflict through her false narratives on ‘Bangla vs ‘Bangladeshi’: Amit Malviya

NationalMother of UAPA accused alleges harassment by Kerala police

NationalKarnataka: 20 Peacocks Found Dead in Hanumanthapura Village

National‘If you are a true Indian…’: SC slams Rahul Gandhi for insulting Indian Army

NationalJharkhand mourns Shibu Soren’s death, Assembly adjourned indefinitely