Govt allows Force Majeure, grants up to 4-month relief to contractors amid West Asia crisis

By IANS | Updated: May 2, 2026 09:10 IST

New Delhi, May 2 In a bid to provide relief to contractors amid the fast-evolving West Asia situation, ...

Open in App

New Delhi, May 2 In a bid to provide relief to contractors amid the fast-evolving West Asia situation, the government has allowed them to invoke ‘Force Majeure’ in view of disruptions, recognising “war” as a valid trigger under procurement rules.

In an office memorandum, the Ministry of Finance said the prevailing conditions in West Asia should be treated as a war-like event for contractual purposes, enabling relief to contractors impacted by delays.

Under the revised guidance, contracts with completion deadlines on or after February 28, 2026, that have been affected directly or indirectly by the West Asia disruptions may be granted an extension of at least two months and up to four months, without any penalty or additional cost to contractors.

“Not with standing the punitive provisions contained in the contract for delay or breach of contract, the supplier would not be liable for imposition of any such sanction so long as the delay… is the result of an event covered in the FM clause,” the memorandum noted.

Moreover, the government also reiterated that delays attributable to ‘Force Majeure' must be assessed on a case-by-case basis, with procuring entities required to re-fix delivery or completion timelines without imposing liquidated damages or denial clauses.

However, the relief comes with conditions.

Invocation of Force Majeure will be considered valid only if contractors were not already in default as of February 27, 2026, and only for disruptions directly linked to the West Asia situation.

Contracts may still be terminated by either party if Force Majeure conditions persist beyond 90 days, without any financial repercussions.

“All contractual obligations shall revive upon completion of the period,” the ministry added.

The clarification builds on provisions outlined in the “Manual for Procurement of Goods, 2024”, “Manual for Procurement of Consultancy Services, 2025”, “Manual for Procurement of Non-Consultancy Services, 2025” and “Manual for Procurement of Works, 2025”, which define Force Majeure as extraordinary events beyond human control, including war, strikes, riots and natural calamities.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

Politics"CM should see sorry state of most prestigious hospital in Lucknow": Akhilesh Yadav slams UP govt

NationalCBI coordinates return of wanted fugitive Kamlesh Parekh from UAE in alleged bank fraud case

NationalPune minor rape-murder: Supriya Sule says strictest action will be taken against accused

BusinessFrom Algorithm to Atmosphere: The Rise of Priya Tummidi as India’s New-Age Event Strategist

PoliticsUP Dy CM Keshav Prasad Maurya welcomes West Bengal repoll, predicts 'crushing defeat' for TMC on May 4

National Realted Stories

National"TVK to win 180-200 seats, Vijay will rule Tamil Nadu": KA Sengottaiyan dismisses post-poll alliance

NationalCommercial LPG price hike set to push up food prices across Chennai

NationalTMC files complaint against Returning Officer, alleges 'unauthorised sorting of postal ballot covers

NationalUP: Schoolchildren allegedly forced into manual labour in Banda; viral video sparks outrage

NationalGreat Nicobar Project key to India's strategic goals: Major General GS Rawat (Retd)