HC pulls up Delhi govt on delay in construction of 100-bedded Najafgarh hospital

By ANI | Updated: September 15, 2021 20:25 IST

The Delhi High Court on Wednesday criticised the Delhi government for its "lethargic attitude" on processing the forest clearance required to complete a 100-bedded hospital in the Najafgarh area.

Open in App

The Delhi High Court on Wednesday criticised the Delhi government for its "lethargic attitude" on processing the forest clearance required to complete a 100-bedded hospital in the Najafgarh area.

A Division Bench of Chief Justice DN Patel and Justice Jyoti Singh called it unfortunate of the public that a 100-bedded hospital in the Najafgarh area was not completed and criticised the Delhi government for showing a lethargic attitude in processing the forest clearance.

However, the Court granted time to the Delhi government to file its reply to the petition indicating the least possible time within which the state government may grant permission/sanction, as required by the Centre under law.

The Court also remarked that the Centre is writing letters after letters and no reply has been given by the Delhi Government, nor it file any counter-affidavit in the writ petition. The Court made it clear to the Delhi government that it cannot sit tight upon the matters asking it to follow the process of law-keeping in mind the welfare of the public at large.

The Court has listed the matter for hearing on November 8.

The Court's remarks came while hearing the litigation filed in public interest filed by a lawyer Rajesh Kaushik, seeking a direction to the governments to complete construction and operation of the 100-bedded general hospital at the site of Rural Health Training Centre (RHTC) in Najafgarh here.

Henceforth, the Centre has urged the Delhi High Court to direct the concerned authority to expedite clearance for transplantation of trees so that the construction work at the RHTC Najafgarh, Delhi can be completed.

Representing the Centre, advocate Anurag Ahluwalia, told the Court that the physical progress of the construction work of the hospital is 80 per cent completed, except the peripheral road, pending for want of clearance from the Department of Forest, Ministry of Environment and Forest, Government of NCT of Delhi, for transplantation of trees.

The Centre government also apprised the Court that the hospital may be completed by the end of the year, subject to the clearance of pending approval by the Department of Forest, Ministry of Environment and Forest, Government of NCT of Delhi as clearance from Delhi government's forest department is pending since December 2018.

The Centre submitted that the work involves shifting/transplantation of few trees and the same could be undertaken only after the forest clearance is available. Henceforth, the Centre has urged the Delhi High Court to expedite clearance for transplantation of trees so that, the construction work at the RHTC Najafgarh, Delhi can be completed.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: courtDelhi High CourtJyoti SinghDelhi delhi high courtUk courtRajesh kaushik
Open in App

Related Stories

EntertainmentSunjay Kapur Property Dispute: Delhi HC Backs Karisma Kapoor’s Children, Rejects Priya Kapur’s Secrecy Bid

EntertainmentAR Rahman Secures Relief as Delhi High Court Overturns Single-Judge Order in Veera Raja Veera Copyright Case

NationalSupreme Court Rejects Jacqueline Fernandez’s Plea to Dismiss Rs 215 Crore Money Laundering Charges Linked to Sukesh Chandrashekhar

NationalSupreme Court Adjourns Hearing on Bail Pleas of Umar Khalid, Sharjeel Imam and Others in Delhi Riots Case

MumbaiBomb Threat At Bombay Hight Court Entire Premises Evacuated

National Realted Stories

NationalPM Modi to attend Dussehra celebrations in East Delhi

NationalSymbol of victory of good over evil: PM Modi extends Vijayadashami greetings

NationalRSS to mark centenary celebrations with Vijayadashami Utsav in Nagpur today

NationalCentre approves mitigation, recovery and reconstruction projects worth Rs 4645.60 crore

NationalRajasthan: Steady decline in crime over last two years, claims police