India's first Metro stretch to be upgraded with aluminum third rails

By IANS | Updated: June 15, 2024 21:30 IST

Kolkata, June 15 India’s first Metro link, between Tollygunge (Mahanayak Uttam Kumar) and Dum Dum stations in Kolkata, ...

Open in App

Kolkata, June 15 India’s first Metro link, between Tollygunge (Mahanayak Uttam Kumar) and Dum Dum stations in Kolkata, is going through a major upgrade nearly 30 years after its completion.

The 16.45 km stretch was completed in 1995 though trains were already running between the intermediate stations (the 3.4 km stretch between Esplanade and Bhowanipur) since 1984.

The Metro Railway has now taken up the replacement of the steel current conducting third rail with an aluminum one. This will not only be energy efficient, but also ensure faster running of trains.

According to Metro engineers, the change will ensure 84 per cent reduction in energy loss, which is Rs 1 crore per year per km.

For the entire stretch, this amounts to Rs 16.45 crore per year.

“Such replacements have already taken place in older Metro stretches in the world like in Singapore, London, Moscow, Berlin, Munich, and Istanbul. The new stretches that we introduced in Kolkata, such as the East-West and Joka-Taratala corridors, have aluminum third rails.

"Work has already started from Noapara (the carshed beyond Dum Dum) and it is expected to be completed in the next two years. A German company has been entrusted with the project. Normal services will not be hampered during the upgradation process,” said Kausik Mitra, CPRO, Metro Railway.

The high-conductive aluminum third rail will have a stainless-steel top. It will have the capacity to reduce system voltage drops and subsequent energy losses, thanks to its superior electrical conductivity.

This reduction in voltage drop in the third rail will allow quicker acceleration. This will also allow the Metro Railway to increase frequency during peak hours. The huge energy savings will bring down operational costs.

The expense involved in replacing the third rail would be realised within three years due to a drop in operational costs.

Additionally, the aluminum third rail will reduce carbon emissions by 50,000 tonnes in its lifetime. The aluminum rail also requires less maintenance and will be highly reliable and stable in a hot and humid city like Kolkata.

Less heat will also be generated inside the tunnel when the Third Rail Current Collector (TRCC) comes into contact with the third rail. No welding will be required to join two aluminum rails, as it can be done with the help of a splice joint. This will help in maintaining air quality inside the tunnel,” Mitra said.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

National‘Poorvi Prachand Prahar’: Forging multi-domain readiness in Eastern Himalayas

AurangabadSIAM donates Rs 1 crore to Chief Minister’s Relief Fund for rain-hit farmers

InternationalPoor quality, frequent malfunctions undermine confidence in Chinese arms: Report

Other SportsAnirban shoots 12-under, McKibbin stays in front at Link Hong Kong Open

National‘We won’t forget or forgive’: 1984 riot survivors attack Congress, urge swift justice

National Realted Stories

NationalBihar polls: ECI transfers four officials after Dularchand Yadav’s murder

NationalPiyush Goyal slams Mahagathbandhan's poll promises; lauds Bihar's development under NDA govt

NationalAbhishek Banerjee moves to the front amid rising rhetorics over SIR

NationalChhattisgarh residents thank PM Modi for boosting infrastructure, housing, and rural development

NationalTrinamool plans mega anti-SIR rally in Kolkata on day one of 1st stage of revision exercise