Kashmir to get its first electric train on Gandhi Jayanti

By IANS | Updated: September 14, 2022 10:50 IST

Srinagar, Sep 14 On October 2, electric train will start moving on the 137 kms long Banihal-Baramulla corridor ...

Open in App

Srinagar, Sep 14 On October 2, electric train will start moving on the 137 kms long Banihal-Baramulla corridor of Jammu and Kashmir rail link.

Indian Railway officials said that work on the project was going on since August 2019.

The mandatory principal chief electrical engineer (PCEE) inspection of the electric rail link will take place on September 26 and on Gandhi Jayanti, the project will be inaugurated, the railway officials said.

"Trials on Baramulla-Budgam part of the 137-Kms long electric train link have already been completed while the trial on the remaining Budgam-Banihal portion will be carried out on September 20", sources said, adding that the project cost of the electric train link from Banihal to Baramulla is Rs 324 crore.

The electrification of the Banihal-Baramulla rail link will reduce air pollution and is expected to bring down the operational cost by 60 per cent.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

Other SportsCalafiori returns to Arsenal training ahead of PSG clash

InternationalBangladesh ex-PM Khaleda Zia returns home after medical treatment

NationalDefence mock drills to be conducted at three locations in K’taka

NationalPradeep Dahiya appointed new MCG Chief

National4 killed, 42 injured in J&K road accident

National Realted Stories

NationalRevanth Reddy most incompetent CM in India's history: KTR

NationalFive underpasses to be built along Metro route in Gurugram

NationalBhopal gas toxic waste disposal underway, four monitoring system in place

NationalKGMOA calls for pre-exposure rabies vaccination programme in Kerala

NationalMP Govt to recruit 850 local tribals to keep watch on Maoists