Minister Vaishnaw informs status of Mumbai-Ahmedabad High Speed Rail progress in Parliament

By ANI | Updated: April 5, 2023 15:40 IST

New Delhi [India], April 5 : Union Minister of Railways Ashwini Vaishnaw informed the Parliament on Wednesday that the ...

Open in App

New Delhi [India], April 5 : Union Minister of Railways Ashwini Vaishnaw informed the Parliament on Wednesday that the groundbreaking ceremony of Mumbai-Ahmedabad High Speed Rail (MAHSR) project was held on September 14, 2017, in reply of a question. According to the minister, physical progress of 32.93 per cent in Gujarat and 13.72 per cent in Maharashtra, pertaining to the project, had been achieved till February this year.

"Till now, out of total 352 km elevated viaduct, approx. 257 km of piling, 180 km of foundation, 155 km of the pier and 37 km of girder launching have been completed in Gujarat and Dadra & Nagar Haveli," the minister informed the members.

The minister in a reply to a question said the total cost of MAHSR project was estimated as Rs 1,08,000 crore in 2015 and also informed the Parliament that an expenditure of Rs 38,506 crore had so far been incurred on MAHSR project.

The minister also said in a reply that the execution of the project had been affected due to a delay in land acquisition in the state of Maharashtra and consequent delays in finalisation of contracts as well as adverse impact of Covid-19.

In a reply to a question, he said the anticipated cost and timeline could be ascertained only after completion of land acquisition, finalisation of all contracts and associated timelines.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: indiaparliamentNew DelhiThe new delhi municipal councilDelhi south-westIndiUk-indiaRepublic of indiaIndia india
Open in App

Related Stories

InternationalIranian President Calls for Constructive Role of Brics to Halt West Asia Conflict During Talks With PM Modi

LifestyleEid 2026 Date: When Will Saudi Arabia, UAE and India Celebrate Eid-ul-Fitr?

MaharashtraMaharashtra CM Devendra Fadnavis Unfurls 200-Foot National Flag at Nagpur’s Kasturchand Park

NationalAhmedabad Traffic Update for India vs New Zealand T20 World Cup Final: Check Road Closures and Alternate Routes Near Narendra Modi Stadium

AurangabadLocal industries feel heat of Global conflict

National Realted Stories

NationalGovt conspiring to hijack Panchayat polls, says Himachal BJP chief

NationalUS chose to use Pakistan as facilitator for own reasons: Israeli envoy on Iran ceasefire

NationalNGT directs MCD to submit time-bound plan for Ghazipur landfill

NationalPunjab launches school attendance tracking system

NationalKeralam Assembly Polls: Speaker Shamseer, Congress MP Sudhakaran cast votes