Mumbai: MMRC completes downline from Colaba to SEEPZ

By ANI | Updated: June 28, 2022 20:00 IST

The Mumbai Metro Rail Corporation achieved its 41st breakthrough after the tunnel boring machine (TBM) Tansa-2 completed its final downline, informed the officials on Tuesday.

Open in App

The Mumbai Metro Rail Corporation achieved its 41st breakthrough after the tunnel boring machine (TBM) Tansa-2 completed its final downline, informed the officials on Tuesday.

The downline drive was 832.5 metres long and completed in 263 days.

With this, the entire downline of Mumbai Metro Line 3 (MML-3) from Colaba to SEEPZ has been completed using a total of 555 concrete rings from Mahalaxmi to Mumbai Central metro station.

"MMRC achieved its 41st breakthrough as TBM Tansa-2 completed its final downline drive of 832.5m in 263 days using 555 concrete rings frm Mahalaxmi to Mumbai Central Metro Station.With this, entire downline of #MML-3 from Colaba to SEEPZ is now complete," tweeted the Mumbai metro from it's official handle.

Mumbai Metro Line-3 will run along the Colaba-Bandra-SEEPZ corridor connecting Mumbai's key financial hubs.

Once implemented, MML-3 will reduce traffic by about 35% or by 4.5 lakh vehicles, leading to the decongestion of roads. Travel time will be reduced to 50 minutes from 100 minutes on the route.

The estimated cost of the project is over 30 thousand crores.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Mumbai metro rail corporationMumbai metro line
Open in App

Related Stories

MumbaiMumbai Metro Lines 9 and 2B to Partially open On April 7

MumbaiMumbai Metro Pillar Collapse: Deputy CM Eknath Shinde Orders Suspension of Executive Engineer

MumbaiMumbai Metro Line 2B Update: Chembur Station Likely To Open in April 2026, Check Details Inside

MumbaiMumbai Metro Line 9 Start Date: Red Line Between Dahisar East and Mira Road Likely to Open on This Day

MumbaiMumbai Metro Line 2A & 7 Services to Start Late on December 12 – Check New Timings and Key Details Here

National Realted Stories

NationalUnprecedented victory, Kerala witnessing new political era: Kharge

NationalMumbai Crime Branch nabs two in West Bengal Ashram bombing case after tracking them to Borivali

NationalHonoured to have addressed European Round Table for Industry in Gothenburg: PM Modi

NationalTN's Ooty flower festival begins today with grand floral displays, heritage themes

NationalBihar: Fire breaks out in passenger train at Sasaram Railway Station, no injuries reported