Work on Mumbai-Ahmedabad Bullet Train Project progressing at rapid pace: Centre

By IANS | Updated: December 29, 2024 12:45 IST

New Delhi, Dec 29 Work is progressing at a rapid pace on the Mumbai-Ahmedabad Bullet Train Project with ...

Open in App

New Delhi, Dec 29 Work is progressing at a rapid pace on the Mumbai-Ahmedabad Bullet Train Project with bridges built across 13 rivers and several highways and multiple railway lines being crossed through seven steel and prestressed concrete bridges, according to the year-end review of Indian Railways.

Over 243 km of viaduct construction has been completed under the project, along with 352 km of pier work and 362 km of pier foundation work.

Track construction in Gujarat is progressing rapidly, with RC (Reinforced Concrete) Track Bed construction underway in Anand, Vadodara, Surat, and Navsari districts. About 71 track km of RC track bed construction has been completed, and welding of rails has commenced on the viaduct.

In Maharashtra, the first concrete base slab for the Mumbai Bullet Train Station has been successfully cast at a depth of 32 metres, equivalent to a 10-storey building. Work on the 21 km tunnel between Bandra-Kurla Complex (BKC) and Shilphata is underway, with an Intermediate Tunnel (ADIT) of 394 metres completed to facilitate main tunnel construction.

Construction of seven mountain tunnels using the New Austrian Tunnelling Method (NATM) is progressing in the Palghar district. The only mountain tunnel in Gujarat has already been successfully completed.

“The 12 stations along the corridor, designed with thematic elements and energy-efficient features, are under rapid construction. These user-friendly and energy-positive stations are designed to provide a world-class passenger experience while prioritizing sustainability,” the review states.

Meanwhile, Indian Railways has set a target of becoming a Net Zero Carbon Emitter by 2030. As of November 2024, approximately 487 MW of solar plants (both rooftop and ground-mounted) and about 103 MW of wind power plants have been commissioned, the review states.

Additionally, 100 MW of Renewable Energy - Round the Clock (RE-RTC) has also started flowing and approximately 2014 MW of renewable capacity has been tied up, it added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

EntertainmentLook Back 2025: Aanand L Rai’s Tere Ishk Mein Ranks Among the Year’s Finest Romantic Films

Other Sports'DC needed someone to open bowling with Starc', says Abhinav Mukund on Auqib Dar’s IPL 2026 deal

NationalArjun Ram Meghwal defends G RAM-G Bill as Oppn cries 'autocracy'

EntertainmentSprash Shrivastava: After ‘Jamtara’, things shifted for me

BusinessFiroze Kohli Drives Next-Gen Marketing Automation with Zapier in 2026

National Realted Stories

National'Tragic event': Giriraj Singh on violent protests in Bangladesh

NationalChhattisgarh Crime: Woman Murdered by Live-in Partner, Body Found Stuffed in Sack

National'Earlier recruitment processes were opaque, now only transparency': Assam CM attacks Cong

NationalHM Amit Shah discusses constitution of port security bureau for ships

National'Rs 39,000 crore meant for Dalits used for guarantees': K'taka BJP demands Minister's resignation