Carnac Bridge to Reopen by June 10; BMC Sets 53-Day Completion Deadline

By Amit Srivastava | Updated: April 19, 2025 19:17 IST

Mumbai: The long-awaited reconstruction of the Carnac railway flyover near Masjid Bunder is racing toward completion, with the Brihanmumbai ...

Open in App

Mumbai: The long-awaited reconstruction of the Carnac railway flyover near Masjid Bunder is racing toward completion, with the Brihanmumbai Municipal Corporation (BMC) setting a firm deadline of June 10, 2025 for reopening the crucial East-West connector to traffic.

At a site inspection held on April 18, Additional Municipal Commissioner (Projects) Abhijit Bangar issued strict directives to the contractor and local officials, emphasizing that all pending work must be completed within 53 days and any delays will not be tolerated.

The Carnac Bridge, which links Lokmanya Tilak Road to P. D’Mello Road, is a vital lifeline for South Mumbai, especially for traffic flowing near Chhatrapati Shivaji Maharaj Terminus, Masjid Bunder, and Mohammed Ali Road. The original bridge was deemed unsafe and subsequently demolished, with reconstruction work taken up by the BMC’s Bridges Department.

Accompanied by Chief Engineer (Bridges) Uttam Shrote, Deputy Chief Engineer (City) Rajesh Mule, and other key officials, Bangar reviewed the ongoing work and laid out a detailed timeline for completion.

Work on the western side of the bridge is currently on track, while progress on the eastern side is being expedited. Of the 40 required girders, five have already reached the site from the fabrication facility in Daman, and eight pillars on the eastern stretch have been constructed.

Bangar emphasized the importance of parallel execution—ensuring that pedestal and bearing works continue alongside girder installation. He also instructed BMC engineers to maintain close coordination with the fabrication unit in Daman to prevent any material delays.

“Senior engineers must conduct regular site visits to ensure quality and pace are maintained,” Bangar stressed. “This bridge is critical to South Mumbai’s transport network, and it must be delivered on time.”

As the countdown begins, Mumbaikars can finally look forward to smoother connectivity in the city’s busy southern quarters.

Key Milestones Ahead:

Steel Girder Delivery Deadline: April 27, 2025

Girder Installation Over Tracks: By May 2, 2025

Railway Portion Concreting: To be completed by May 7, 2025

Approach Roads Completion: Targeted by June 5, 2025

Full Bridge Opening: Scheduled for June 10, 2025

Tags: Carnac BridgeCarnac Bridge demolitionBrihanamumbai municipal corporationSouth MumbaiMasjid bunderP Dmello RoadMumbai News
Open in App

Related Stories

MumbaiMumbai: Encounter Specialist Daya Nayak Retires After 30 Years of Service; Promoted to ACP Just Before Retirement

MumbaiMumbai: Eknath Shinde Reverses BMC’s ₹15,000 Pothole Fine, Restores ₹2,000 Fee for Ganesh Mandals

Navi MumbaiNavi Mumbai: Environmental Groups Hail Protection of Key Wetlands in Revised Development Plan

MaharashtraMalegaon Blast Case Verdict: Security Beefed Up Outside NIA Court in Mumbai (Watch Video)

MumbaiMumbai: Five Candidates Booked for Submitting Fake Mark Sheets for Peon Posts at Bombay High Court

Navi Mumbai Realted Stories

MumbaiMumbai Local Train Fight: Brawl Erupts Between Passengers on Moving Virar-Dahanu Local Over Boarding Dispute; Video Goes Viral

PunePune Rave Party Case: Pranjal Khewalkar Among 5 Accused Sent to 14-Day Judicial Custody

MaharashtraMaharashtra: 27-Year-Old Indian Army Jawan Dies of Heart Attack After Returning from 5-Day Leave in Rajpur

Maharashtra'Congress Tried to Push Narrative to Appease Vote Bank': Maharashtra CM Devendra Fadnavis on Malegaon Blast Case Verdict

PunePune Traffic Update: Police Issues Advisory for Lokshahir Annabhau Sathe Jayanti 2025; Check Route Diversions