Mumbai: BMC Sets May 31 Deadline for Cement Concrete Roads, Abhijit Bangar Ramps Up Inspections

By Amit Srivastava | Updated: April 9, 2025 18:47 IST

With the Brihanmumbai Municipal Corporation (BMC) setting a deadline of May 31, 2025, to complete all ongoing cement concrete ...

Open in App

With the Brihanmumbai Municipal Corporation (BMC) setting a deadline of May 31, 2025, to complete all ongoing cement concrete road works, Additional Municipal Commissioner (Projects) Abhijit Bangar has stepped up field inspections across the city to ensure progress stays on track. He has been personally visiting road works in both the eastern and western suburbs, accompanied by experts from IIT Bombay and representatives from the Quality Monitoring Agency (QMA).

During a recent late-night visit to Road No. 27 in Sion (East), F-North Ward, Bangar reviewed the status of ongoing concreting and stressed the importance of strengthening the ready-mix concrete (RMC) supply chain to meet the upcoming deadline. He urged contractors and project operators to work in close coordination and act swiftly to increase the pace of work.

As part of quality control efforts, Bangar inspected each layer of the road structure — from the granular sub-base to dry lean concrete (DLC) and the final pavement-quality concrete. IIT Bombay Associate Professor Solomon Debbarma noted that the quality and evenness of the base layers, especially the DLC, are crucial for road durability.

In addition to roadwork, Bangar reviewed the progress of water pipeline installations under footpaths in the same ward. Given that most of the water lines lie beneath footpaths, he instructed that pipelines be laid only for those stretches scheduled to be completed by May 31, to avoid future disruptions.

Following the field inspection, Bangar paid a surprise visit to the Biltech LLP RMC plant at the Bandra-Kurla Complex. He examined the automated batching systems, temperature control mechanisms, and cleanliness standards, and observed quality tests like slump and temperature checks before dispatch.

To maintain momentum, Bangar directed an increase in RMC vehicle numbers and a reduction in their turnaround time. Strengthening the supply chain and ensuring seamless coordination between RMC suppliers and road contractors, he said, is essential to delivering quality roads within the deadline.

Tags: Mumbai roadsBrihanmumbai Municipal CorporationRoad WorksMumbai NewsIit Bombay
Open in App

Related Stories

MumbaiMumbai Mock Drills Till May 13 Amid Airport Bomb Threat Following Operation Sindoor

MumbaiMumbai: Wadala Man Loses ₹20 Lakh in Shares to Cyber Fraud While On Narmada Pilgrimage In Gujarat

MumbaiMumbai: Senior Citizen Duped of Rs 67 Lakh in Share Trading Scam; One Accused Arrested

MumbaiMumbai: Man Cheats Woman of Rs 27.4 Lakh on Matrimonial Site with False Marriage Promise; FIR Filed

MumbaiMumbai EOW Arrests 2 Key Accused in Multi-Crore Mithi River Desilting Scam

Navi Mumbai Realted Stories

MaharashtraMaharashtra Accident: 4 Dead, 20 Injured as Speeding Dumper Crashes Into MSRTC Bus in Raigad

MaharashtraPalghar Shocker: Suspended BEST Worker Strangles Son To Death, Dies By Suicide Later

ThaneThane: Crime Branch Arrests Two Cops for Selling Sensitive Mobile Data to History-Sheeter

ThaneThane: Crime Branch Busts Fake Currency Racket, Seizes ₹45.5 Lakh in Counterfeit Notes

NashikNashik Citizens Unite in Prayer and Gratitude for Soldiers at ‘Sindoor Samarpan’ After Indian Army's Decisive Strike On Pak Terror Hideouts