Mumbai-Ahmedabad bullet train project progressing well: Railways

By IANS | Updated: September 5, 2020 18:05 IST

New Delhi, Sep 5 The Indian Railways on Saturday said that the 508-km Mumbai-Ahmedabad High Speed Rail project, ...

Open in App

New Delhi, Sep 5 The Indian Railways on Saturday said that the 508-km Mumbai-Ahmedabad High Speed Rail project, popularly known as the 'Bullet Train' project, was progressing well, but the real timeframe for the completion of the project can be gauged within the next three to six months when the status of land acquisition will be ascertained.

Addressing a virtual press conference, Railways CEO V.K. Yadav said, "While 82 per cent of the land has been acquired in Gujarat, in Maharashtra land acquisition is only at 23 per cent." He said that in a linear project like the bullet train, work can only begin when a certain amount of land is available.

"We are hoping that within the next three to six months, we will be able to get to that point. Our designs are ready and we are set to go. It is true that the tenders and land acquisition was delayed a bit due to the Covid-19 pandemic, but I can say that the project is progressing well," Yadav said.

He asserted that as the Covid-19 situation improves, the Railways will be able to start the bidding process within the next three to six months.

He said, "We will be able to get the status of land acquired and then we will be able to provide a real timeframe for the completion of the project."

( With inputs from IANS )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Indian RailwaysMinistry of indian railwaysIndian railways ministryIndian railway networkBangladesh railways
Open in App

Related Stories

NationalIndian Railways Suspends 4 Officials for Providing 'Unfit' Train Coaches to BSF Jawans (Watch Video)

MumbaiIndian Railways to Introduce New-Design Non-AC Local Trains With Automatic Doors by January 2026

NagpurNagpur Railway Passengers Cancel Tickets Worth Rs 60 Crore Due to Delayed, Unreliable Train Services

NationalWill Mandatory e-Aadhaar Verification by Indian Railways End Tatkal Ticketing Chaos?

NationalPM Narendra Modi To Launch Multiple Projects Worth Over Rs 77,000 Crore in Gujarat

Politics Realted Stories

MaharashtraNCP Leader Suraj Chavan Shares Alleged Black Magic Video of Shiv Sena Leader Bharat Gogawle Amid Row Over Raigad Guardian Post

MaharashtraMaharashtra Politics: Raj Thackeray Meets CM Devendra Fadnavis at Taj Lands End Amid Rumours of MNS–Sena UBT Alliance

MaharashtraMaharashtra Municipal Elections 2025: Mahayuti Alliance to Contest Civic Body Polls Together, Says CM Devendra Fadnavis

Maharashtra'Remembered the Advice My Mother Gave Me': Supriya Sule On Her WhatsApp Status

Maharashtra'Will Give News Soon': Uddhav Thackeray's Big Statement on Possible Alliance of Shiv Sena UBT and MNS