UP's Purvanchal Expressway gets only half of expected traffic

By IANS | Updated: June 20, 2022 13:05 IST

Lucknow, June 20 The 341 km long Purvanchal Expressway, a flagship project of the Yogi Adityanath government in ...

Open in App

Lucknow, June 20 The 341 km long Purvanchal Expressway, a flagship project of the Yogi Adityanath government in Uttar Pradesh, is facing teething troubles and is not attracting even half the traffic that was estimated.

The tolling agency, Prakash Asphaltings and Toll Highways (India) Ltd, has quit the contract citing collection of only 45 per cent of the targeted toll.

Between May 1 and 26, the agency collected less than Rs 7.5 crore against the target of Rs 17 crore.

According to sources, the recent board meeting of UP Expressways Industrial Development Authority (UPEIDA), zeroed in on three reasons for low toll collection.

Three reasons are the non-completion of the Lucknow Outer Ring Road, the incomplete bridge on Ganga at Buxar Bihar, and the high toll for heavy vehicles.

These three reasons are limiting the traffic from using the new expressway.

According to UPEIDA sources, the National Highways Authority of India (NHAI) has informed that the Lucknow Ring Road and the bridge near Buxar will be ready by December 2022.

The UPEIDA is also considering reducing the toll price on heavy vehicles as it is almost 20 per cent more than the toll levied by NHAI on the National Highways.

Light motor vehicles such as cars pay Rs 675 as toll tax on the Purvanchal Expressway, light commercial vehicles pay Rs 1,065, while heavy vehicles have to pay Rs 2,145 as toll tax on the road.

The Purvanchal Expressway was inaugurated in November 2021 by Prime Minister Narendra Modi.

The expressway starts from village Chaudsarai in Lucknow, located on Lucknow-Sultanpur Road (NH-731) and ends at village Hydaria situated on National Highway No. 31, near the Uttar Pradesh-Bihar border.

The expressway is six-lane wide and can be expanded to eight-lane in future.

Constructed at an estimated cost of Rs 22,500 crore, the Purvanchal Expressway is designed to benefit the eastern part of Uttar Pradesh, especially Lucknow, Barabanki, Amethi, Ayodhya, Sultanpur, Ambedkar Nagar, Azamgarh, Mau and Ghazipur districts.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Buxar biharUp expressways industrial development authoritylucknowLTDNarendra ModiLucknow kanpurLucknow municipalNarendra modi modiBjp national general secretary organizationNarendra modLucknow district administration
Open in App

Related Stories

NationalMumbai to Lucknow Air India Flight AI-2491 Cancelled Due to Operational Reasons

HealthInternational Yoga Day 2025: Know Theme, Date, and How Yoga Can Benefit Life on Earth

PunePune Bridge Collapse: PM Modi Speaks to CM Fadnavis as Death Toll Rises to 4

National"Unimaginable That Vijay Bhai Is No More”: PM Modi Mourns Former Gujarat CM's Death In Ahmedabad Plane Crash

NationalRajasthan Family’s Last Selfie Before Ahmedabad Plane Crash Goes Viral, Captures Final Moments

Politics Realted Stories

MaharashtraNCP Leader Suraj Chavan Shares Alleged Black Magic Video of Shiv Sena Leader Bharat Gogawle Amid Row Over Raigad Guardian Post

MaharashtraMaharashtra Politics: Raj Thackeray Meets CM Devendra Fadnavis at Taj Lands End Amid Rumours of MNS–Sena UBT Alliance

MaharashtraMaharashtra Municipal Elections 2025: Mahayuti Alliance to Contest Civic Body Polls Together, Says CM Devendra Fadnavis

Maharashtra'Remembered the Advice My Mother Gave Me': Supriya Sule On Her WhatsApp Status

Maharashtra'Will Give News Soon': Uddhav Thackeray's Big Statement on Possible Alliance of Shiv Sena UBT and MNS