Cross connection delay causes water shortage in city for second day

By Lokmat English Desk | Updated: February 14, 2024 23:15 IST

Work in Farola completed; cross connection work in Jayakwadi extended late into the nightChhatrapati Sambhajinagar: The cross connection ...

Open in App

Work in Farola completed; cross connection work in Jayakwadi extended late into the night

Chhatrapati Sambhajinagar: The cross connection work for the 900 mm diameter water line, aimed at ensuring abundant water supply, commenced on Wednesday and continued throughout the day. The work in Farola was completed as scheduled, but the cross connection work in Jayakwadi extended late into the night. As a result, the city is expected to face water shortage on Thursday.

The Chhatrapati Sambhajinagar Municipal Corporation (CSMC) conducted various works during the scheduled shutdown from 10 am to 6 pm on Wednesday. To address potential water shortages this summer, a new 900 mm diameter water line was installed. However, testing of the water line is still pending. Before conducting the testing, cross connection works were necessary at Jayakwadi and the Farola water treatment plant. To facilitate this, a scheduled shutdown was implemented from 10 am to 6 pm on Wednesday, resulting in the suspension of water supply to the city, including Cidco-Hudco. The Maharashtra Jeevan Pradhikaran was responsible for the cross connection works, with the work at Farola completed during the day. The work at Jayakwadi is expected to take place from 12 pm to 1 am.

During the shutdown, the corporation carried out various tasks, including cross connection work at two locations on the Beed Bypass road for the separate express canal serving Cidco-Hudco. A damaged valve on a 1200 mm diameter water line at Farola Phata was replaced, and a leak in the MBR at Nakshatrawadi was repaired through welding, as informed by the executive engineer, M Falak.

Following the shutdown, the canal from Jayakwadi to Nakshatrawadi, as well as from Nakshatrawadi to Cidco N-5, was completely emptied. It will take time to refill these water channels before the city's water supply can resume. The process is expected to be completed by Thursday morning or afternoon, depending on the phased filling of the aqueducts. Already, several colonies are experiencing water scarcity for eight to ten days, and this situation will be extended by another two days.

Open in App

Related Stories

Other SportsPremier League: Man City, Arsenal set for potential title-defining clash

EntertainmentNeha Dhupia supports Patralekhaa against body shaming: Fix your own thinking

NationalDelhi HC restrains anonymous social media accounts from posting defamatory content against advocate couple

NationalCM Mohan Majhi reaffirms ‘Samruddha Odisha’ vision, pays tribute to Biju Patnaik

NationalBengal polls: Counting centres reduced to 87​

Aurangabad Realted Stories

AurangabadInner Wheel Club of Aurangabad Lotus conducts religious waste recycling drive

AurangabadNSBT hosts ‘Navotsav 2026’

AurangabadTemperature climbs back to 41.4°C in city - A

AurangabadCMIA-MIT launch joint skill development initiative

Aurangabad‘This marriage cannot happen’