Water reaches Nakshatrawadi after a 30-year wait

By Lokmat Times Desk | Updated: April 14, 2026 20:15 IST

City to receive water within a monthNew pipeline areas to wait longerLokmat News NetworkChhatrapati Sambhajinagar:In ...

Open in App

City to receive water within a month

New pipeline areas to wait longer

Lokmat News Network

Chhatrapati Sambhajinagar:

In a major milestone for over 1.8 million residents, water from Jayakwadi dam reached the Nakshatrawadi water treatment plant on Tuesday, marking the occasion of the birth anniversary of Dr. Babasaheb Ambedkar. The achievement comes after 30 years of anticipation and five years of continuous effort.

Officials and staff of Maharashtra Jeevan Pradhikaran, the municipal corporation, and GVPR celebrated with fireworks as water gushed into the plant. The long-awaited moment left many emotional. However, it will take about a month for water to reach household taps, while areas with newly laid pipelines may have to wait until Diwali.

Testing of the 2500 mm diameter pipeline had been underway since March 23. Though scheduled for 10:00 am, water reached the plant at 1:50 pm on Tuesday. As it began flowing, chants of “Ganpati Bappa Morya,” “Har Har Mahadev,” and “Godamai ki Jai” filled the air. Municipal commissioner Amol Yedage performed the ritual, while chief engineer Manisha Palande and GVPR’s Mahendra Gogalathu were present. The flow continued till 2:45 pm before being stopped.

Water successfully lifted 86 feet

The treatment plant, located 86 feet above the main road, received water without any leakage despite high pressure, marking a successful trial.

Next steps underway

Pipeline cleaning from Jayakwadi to Nakshatrawadi is complete. Reverse cleaning will now be carried out using full pressure, with scour valves opened every 4–6 km.

Before full supply begins, minor works, testing, purification, chlorination, and licensing will be completed over the next 8–10 days. An additional 50–60 MLD water will be fed into the existing MBR system, ensuring supply every two to three days. Areas with new pipelines will receive water later.

Phase one complete, bigger task ahead

The 38 km pipeline from Jayakwadi to Nakshatrawadi marks a crucial first phase. The next challenge is citywide distribution through a 1500 mm main pipeline and five reservoirs. A roadmap has been prepared to complete the project within a year.

“A moment of immense joy”

Chief engineer Manisha Palande said, the success came after overcoming technical challenges with government support and will significantly boost supply.

“Result of tireless efforts”

GVPR’s general manager Mahendra Gogalathu said continuous work since 2023 made it possible, with efforts ongoing to deliver water to citizens at the earliest.

Open in App

Related Stories

NationalCM Mohan Yadav to announce Madhya Pradesh Board class 10-12 results today

International'India vitally important to us, an incredible partner': US Ambassador Sergio Gor

Cricket"Gives a lot of confidence": CSK spinner Noor Ahmed after match-winning spell against KKR

PoliticsBill providing for increase in Lok Sabha seats will "disenfranchise" states which have done well in population control: Karti Chidambaram

InternationalPakistan: Man jailed for 10 years in rape case in Karachi

Aurangabad Realted Stories

AurangabadDr Ambedkar's Birth Anniversary Celebrated with Great Enthusiasm & Reverence

AurangabadOrders fell silent, DJs did not

Aurangabad'Tohfatul Hadees' book released

AurangabadStudents audit to be conducted in 1,819 schools today

AurangabadAll India inter-university cycling tournament to begin today