Kerala HC seeks State Attorney's reply on contempt petition of Adani Ports

By IANS | Updated: September 15, 2022 13:00 IST

Thiruvathapuram, Sep 15 The Kerala High Court on Thursday asked the State Attorney to respond to Adani Port's ...

Open in App

Thiruvathapuram, Sep 15 The Kerala High Court on Thursday asked the State Attorney to respond to Adani Port's contempt petition against the state government for failing to provide security for the construction of the upcoming Vizhinjam Port.

On September 1, the court held that the right to protest does not grant the right to obstruct a legally permitted project - the upcoming Vizhinjam Port.

It then ordered police protection for the workers and other officials of Adani Ports engaged in the construction of Vizhinjam port.

While giving an interim order, Justice Anu Sivaraman had pointed out: "I have no doubt in my mind that the right to agitate or protest any matter, including the apathy or neglect of the government, cannot confer any right to any of the protesters, to contend that they have the right to obstruct the activities which have due permissions or to trespass into the construction site and cause damage to public property...This Court has time and again considered the issue of competing interests in the grant of police protection and has held that a right to protest can only mean a right to protest peacefully and that there can be no right to obstruct a legally permitted project or activity in the guise of a protest, whatever be the reason for the protest."

But the resistance and the protests continued and work was unable to be resumed forcing the Adani Ports to approach the court with a contempt petition, read the interim judgment.

On Thursday, the court asked the State Attorney about this and he sought time to file the reply. The court then posted the case for Tuesday.

The petition was moved by Adani Ports and by its contracting partner Howe Engineering Projects.

Adani Vizhinjam Port Pvt. Ltd. was selected as the concessionaire for the Vizhinjam Seaport Project and construction began on December 5, 2015.

However, the project has been opposed by the fishermen community which, under the leadership of the Catholic Archdiocese of Trivandrum, are demanding, among other things, proper environmental impact studies, rehabilitation of families who lost their homes to coastal erosion and repairing coastal damage.

The petitioners pointed out that the protesters have been blocking the entry and exit points to the construction site and that on some occasions, thousands of protesters actually managed to enter the site which is a high security zone.

They submitted that all construction work has been stalled since August 17 due to the protests.

According to the petitioners, the environmental clearance for the project was granted in 2014, before Adani Ports entered the fray, after several environmental studies were conducted.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Adani PortsKerala High CourtAnu SivaramanKerala high courts
Open in App

Related Stories

NationalNo Toll Collection on Bad or Congested Roads: Supreme Court

EntertainmentMalayalam Actor Siddique Goes Missing After Court Denies Bail In Rape Case; Police Launch Search

EntertainmentHema Committee Report: Siddique To Face Jail Term in Sexual Harassment Case? Kerala High Court Rejects Actor's Bail Plea

EntertainmentHema Committee Report: Kerala HC Dismisses Actor Siddique’s Anticipatory Bail Plea in Rape Case

NationalHema Committee Report: Kerala High Court Raps Kerala Government, Says ‘You Have Done Nothing in 4 Years’

International Realted Stories

InternationalIndia and Japan announce AI Cooperation Initiative, PM Modi invites Ishiba for AI Impact Summit

InternationalIndian Air Force intensifies flood relief ops across Punjab, J-K

InternationalPM Modi invites Japanese PM Ishiba for AI Impact Summit in India next year

InternationalIndia and Japan need to take advantage of each other's strengths: Ishiba

InternationalTorrential rain triggers flash flooding across parts of Laos