Bombay HC stays Shinde govt's decision suspending development project in Pune by previous dispensation

By Lokmat English Desk | Published: December 3, 2022 03:01 PM2022-12-03T15:01:52+5:302022-12-03T15:02:14+5:30

The Bombay High Court has stayed the implementation of two orders passed by the Eknath Shinde-led Maharashtra government suspending ...

Bombay HC stays Shinde govt's decision suspending development project in Pune by previous dispensation | Bombay HC stays Shinde govt's decision suspending development project in Pune by previous dispensation

Bombay HC stays Shinde govt's decision suspending development project in Pune by previous dispensation

The Bombay High Court has stayed the implementation of two orders passed by the Eknath Shinde-led Maharashtra government suspending work relating to a development project at a village in Pune district initiated by the erstwhile Maha Vikas Aghadi (MVA) dispensation led by Uddhav Thackeray.

The bench was hearing a petition filed by Belewadi village panchayat in Pune, which had sought quashing of the orders dated July 19 and 25 passed this year by CM Shinde and Deputy Chief Minister Devendra Fadnavis. By these orders, the state government had suspended the development work across the state initiated by the predecessors in the office, including that of Belewadi village panchayat.

In our prima facie view, the state government, already having issued orders after having approved the budget for the said work to be carried out in the village of the petitioner panchayat, cannot suspend such work which would result in lapse of the budget already earmarked for the said work and that also without any basis, the court said.

According to a report of PTI, A division bench of Justices R D Dhanuka and S G Dige in its order passed on November 28 noted that suspension of such work would result in the lapse of the budget which was earmarked for the project.

As per the plea, the previous MVA government had on March 31, 2022 sanctioned development work of construction of gutters in the village. Work order for this work was issued on July 14 to the contractor. However the state government on July 19 and 25 suddenly suspended the work without recording any reasons, the petition claimed.