Nagpur Railway Station To Get Major Upgrade, Aims to Enhance Passenger Comfort and Preserve Heritage

By Lokmat English Desk | Updated: November 28, 2024 13:35 IST

The Rail Land Development Authority (RLDA), operating under the Ministry of Railways, is making significant strides in the redevelopment ...

Open in App

The Rail Land Development Authority (RLDA), operating under the Ministry of Railways, is making significant strides in the redevelopment of the Nagpur Railway Station, a project valued at Rs 487.77 crore. This initiative aims to modernize the station's infrastructure while preserving its historical significance.

Construction Progress

The redevelopment project is progressing well, with notable advancements on both the east and west sides of the station:

East Side: Ongoing basement construction is set to enhance parking facilities, providing better access for passengers.

West Side: Basement construction is also underway here, executed in two phases to minimize disruption. Phase-I has been completed, and Phase-II is currently in full swing. A key aspect of this phase includes relocating the Monumental National Flag ('Tiranga') to a more prominent position.

The existing Passenger Reservation System (PRS) system of west side of the station is also planned to be shifted to Southern side on the Platform no I exit gate. 

Also Read | Mumbai Local Train Update: Central Line Platform Numbers at Dadar Station Changed for Passenger Convenience; Check Details.

RLDA has prioritized passenger convenience throughout the redevelopment process. The upgraded infrastructure will feature improved parking, enhanced amenities, and modernized facilities while retaining the station's heritage charm. The project is designed as a brownfield initiative, ensuring that train operations remain uninterrupted and passenger experience is minimally affected.

Once completed, the revamped Nagpur Railway Station is expected to accommodate up to 98,000 passengers daily. It will include separate arrival and departure areas, dedicated foot-over bridges (FOBs), and a spacious concourse equipped with various amenities and retail options. The project is scheduled for completion by December 2025.

Officials have confirmed that approximately 35% of physical work has been completed so far, with ongoing efforts focused on both structural enhancements and preserving the historical essence of this Grade-II heritage site. As the redevelopment continues, RLDA remains committed to delivering a state-of-the-art railway station that honors Nagpur's rich history while meeting modern passenger needs.

Tags: NagpurRail land development authorityMaharashtra
Open in App

Related Stories

MaharashtraLatur: Minor Dalit Girl Kidnapped and Raped By 18-Year-Old Man, Case Against Cafe Land Owner

PunePune Shocker: Teen Stabs Classmate to Death Inside Coaching Center In Rajgurunagar Over Heated Argument

MaharashtraMaharashtra: Father and Son Killed After Car Crashes into Container While Returning from Mumbai Airport

MumbaiMumbai: 41-Year-Old Man Defrauded of Rs 86.85 Lakh in Share Market Investment Scam; Case Registered

MaharashtraLok8 Brookside Officially Launched, Gets Overwhelming Response

Nagpur Realted Stories

NagpurNagpur: Drone Spotted Over Solar Industries Airstrip, FIR Registered, Investigation Underway

Nagpur9 per cent making charge on gold jewellery

NagpurSaraswati celebrates annual sports meet

NagpurVid girls lost to MP by 85 runs

NagpurMalhar, Sejal claim singles title