Jaipur, Nov 20 Two people, including an engineer, died while demoulding the world's largest bell at Kota's Chambal ...

Open in App

Jaipur, Nov 20 Two people, including an engineer, died while demoulding the world's largest bell at Kota's Chambal riverfront in Rajasthan, sources said on Monday.

Casting engineer Devendra Arya, who was standing on the box along with a labourer, fell from a height of about 35 feet on Sunday.

Both were rushed to a private hospital in Talwandi, Kota where they were declared dead.

Kunhadi police station officer Mahendra Kumar said the incident took place when the work of removing the bell from the mould box was in progress.

At 3 o'clock in the afternoon, engineer Devendra Arya and labourer Chhotu were busy removing the bell from the box. The bell was being removed with the help of a hydraulic crane.

Suddenly, the topmost girder (iron joint) slipped the moment it touched the hydraulic machine and broke into three.

This led to the two losing their balance and falling from a height of 35 feet. They suffered serious injuries.

While Chhotu died as soon as he was taken to the hospital, the engineer succumbed to his injuries during treatment at 5 p.m.

Notably, the bell is in the mould box and had to be removed this month.

The work of taking the world's largest bell out of the mould resumed this month.

UIT and the contractor had called the mould making engineer Devendra Arya on November 3.

Prior to this, Urban Development Trust (UIT) and another contractor had tried demoulding for 80 days before giving up and calling Devendra again. After which the work was resumed.

The bell weighing 79,000 kg was created by Devendra Arya by setting up a temporary factory on the riverfront.

Later, there was a dispute between architects Anoop Baratiya and Arya over taking the credit for it and the latter had returned without removing the bell from the mould.

Arya had claimed that the bell would be removed only after the chemicals he had used while casting the bell were made to react in a specific manner and no one has this information except him.

Earlier, he had accused the UIT and the contractor alleging that the credit for making the bell was given to its designer and the UIT contractor has also withheld payment of Rs 1.5 crore.

Arya had refused to take the bell out of the mould until the payment was received. "If I don't take it out, no one will be able to do so."

After the statement, Arya had also called a press conference, but cancelled it later.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

BusinessTrehan Iris Partners with Knox to Introduce a New Era of Wellness-Focused Living

CricketIndia A Captain Jitesh Sharma Wins Toss, Opts to Bowl Against Bangladesh A in Rising Stars Asia Cup 2025 Semi-Final - Check Playing XIs

TechnologyIndian scientists develop cathode material for zinc batteries with increased storage

Other SportsBCCI invites applications for head of cricket education role at CoE in Bengaluru

BusinessIndian scientists develop cathode material for zinc batteries with increased storage

National Realted Stories

NationalKerala HC moots statewide alert system to trace missing persons

National'Some parties on mission to protect infiltrators': Amit Shah on Bengal CM’s plea to halt SIR 

NationalNo confusion in Congress, says K'taka HM on 'leadership crisis' in party

NationalElection Commission debunks vote-voter mismatch theory in Bihar polls

National23-year chase ends as Delhi Police cracks 2002 Sarita Vihar double murder case; two fugitives arrested