NPCIL starts loading nuclear fuel at its 700 MW unit in Rajasthan

By IANS | Updated: August 2, 2024 17:00 IST

Chennai, Aug 2 Nuclear fuel loading at the 700 MW plant at the Rajasthan Atomic Power Project has ...

Open in App

Chennai, Aug 2 Nuclear fuel loading at the 700 MW plant at the Rajasthan Atomic Power Project has commenced, atomic power major Nuclear Power Corporation of India Ltd (NPCIL) announced on Wednesday.

According to NPCIL, the fuel loading process began on Tuesday at the plant located in Rawatbhata in Rajasthan.

The Initial Fuel Loading process began after receiving permission from the Atomic Energy Regulatory Board (AERB) and on completion of all other requirements, NPCIL said.

The Initial Fuel Loading process will be followed by the First Approach to Criticality (start of nuclear fission for the first time) and subsequent power generation.

According to NPCIL, commercial production of power by Unit 7 will happen this year.

The atomic power major also said the other 700 MW plant (Unit 8) is expected to come on line next year.

NPCIL said Unit 7 at RAPP is the third in the series of 16 700 MW Pressurised Heavy Water Reactors (PHWR) being built in the country.

The first two of the 700 MW PHWRs commenced commercial operations at Kakrapar (Units 3 and 4) in Gujarat in 2023-24, NPCIL said.

The two units in Kakrapar are working at good capacity factor.

Late last month, the 220 MW Unit 3 at the Rajasthan Atomic Power Station (RAPS) was connected to the grid after undergoing major renovation and modernisation, including the replacement of the coolant channel, feeder, and other upgrades.

Unit 3 or RAPS 3 has now enhanced safety measures with 30 years of extended life, NPCIL said.

The RAPS 3 commenced commercial power production in June 2000 and was in operation for 22 years before it was taken up for renovation and modernisation in 2022.

In March 2024, India stepped into the second phase of the three-stage nuclear power programme with 'core loading' at the first indigenous 500 MW Prototype Fast Breeder Reactor (PFBR) set up in Kalpakkam near Chennai.

The core loading process includes fuel loading.

The 500 MW PFBR is built by fast breeder reactor company Bhartiya Nabhikiya Vidyut Nigam Ltd (BHAVINI).

Once commissioned, India will only be the second country after Russia to have a commercially operating fast breeder reactor.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

Other SportsIPL 2025: It gives you a lot of satisfaction, says Rahane on one run win over RR

National‘Concentrate on cricket’: Odisha Minister slams Trinamool MP for his remarks on Bengali migrant workers

InternationalIsraeli forces find Hamas weapons near former school, hospital in Rafah

InternationalJapanese delegation visits IIT Guwahati, boost Indo-Japan collaborations in research & innovation

CricketICC chairman Jay Shah performs Ganga Puja in Haridwar

Technology Realted Stories

Technology'WAVES 2025' promises bright future for creative economy, sees multi-crore deals

TechnologyData breach: Nearly 20 million SKT subscribers sign up for USIM protection

TechnologyMOIL kicks off FY 26 with highest-ever production of manganese ore in April

TechnologyPM Modi’s vision driving growth of science and technology: Ajay Kumar Sood

TechnologyWAVEX 2025 aims to build dedicated angel network for media and entertainment startups