300 contractors quit project

By Lokmat English Desk | Updated: June 23, 2024 23:10 IST

300 contractors quit projectThe GVPR company has been complaining about a lack of skilled manpower for the ...

Open in App

300 contractors quit project

The GVPR company has been complaining about a lack of skilled manpower for the past three years. The agency which provided the manpower did not get the money, therefore, it withdrew from the project. So far, 300 small and big contractors have left the work of GVPR.

Box

Digging of 19 city roads

About 19 roads in the city were dug up by GVPR to lay water pipes. The selection of concrete roads was done. There is a question as to who will re-construct after digging roads.

If the GVPR gives an assurance to pay the repair amount to the CSMC, it will repair roads.

But, there has been no decision on this for the past few months. Cement concrete roads built

in crores of rupees are in bad condition and minor accidents are happening there.

Box

Present work status of the scheme

Project cost: Rs 2740 crores

--Fund received so far: Rs1424 crores

--Fund paid to GVPR: Rs 1130 crores

--Dues of others with GVPR: Rs 400 Cr

--Work completion deadline: February 2024

--Main pipeline work: 38 km

--Remaining pipeline work: 6 km.

--Water pipeline laid in the city: 775 out of 1911

--Water tanks to be constructed: 53

--Construction of water tanks completed: 08

Box

Why does work completion appear impossible on time?

The rainy season is going on. The claim to construct one km main water line per month seems false. Jackwell's work is still in the basement. The permission from the Environment and Forest Departments was received late. There is no roadmap to complete the work of 45 water tanks in the city by the end of December. There is no planning for laying an internal water pipeline.

It is not decided who will repair the dug roads. The Government has given 50 per cent of the total amount. It is not yet known when the remaining amount will be received. Considering all these facts, it seems that the work will not be completed by December 2024.

Open in App

Related Stories

InternationalChina bigger threat than USSR: Ex-US Defence Secy

AurangabadWoman killed after speeding car crashes into stationary container

Other SportsItalian Open: Sinner rules in Rome, continues historic Masters 1000 run with sixth successive title

InternationalPM Modi thanks Sweden for support during Pahalgam terror attack, reiterates commitment to fight terrorism

NationalPM Modi's dream project, 'Kalpasar Project,' gets new boost with Dutch technology

Aurangabad Realted Stories

AurangabadYouth drowns in Godavari River at June Kaygaon

AurangabadCity's busiest chowk, nobody's problem

AurangabadJewellery worth lakhs stolen from safe

AurangabadMSRTC’s daily fuel expenditure reaches Rs 31 L

AurangabadPadegaon garbage depot fire; residents' health at risk