CSMC hopes construction of 11 ESRs completes by October!

By Lokmat English Desk | Updated: July 1, 2023 22:50 IST

Chhatrapati Sambhajinagar:The Chhatrapati SambhajinagarMunicipal Corporation (CSMC) officials showed an inability in quenching the thirst of more than ...

Open in App

Chhatrapati Sambhajinagar:

The Chhatrapati Sambhajinagar

Municipal Corporation (CSMC) officials showed an inability in quenching the thirst of more than half of the population of the city as the Maharashtra Jeevan Pradhikaran (MJP) has submitted a claim in the High Court stating that a few elevated storage reservoirs (ESRs) which are being constructed under the new water supply scheme would be transferred to the municipal corporation before the next summer. Meanwhile, the CSMC hopes that they would get possession of 11 ESRs at least by the month of October, said the CSMC executive engineer (water supply) M B Kazi while briefing the media persons on Friday.

Kazi was briefing upon the progress of the new water supply scheme valuing Rs 2,740 crore. The executive engineer said, “The construction of Coffer Dam in Jayakwadi Dam-Nathsagar has been completed and the works to increase its height and strengthen it are in progress. The municipal corporation has leased out its four pumps to the contractor for removing the silt. The daunting task will be completed soon. The laying of the main pipeline of length 19 km, out of 39, has been done. Besides, the main pipes of a 2500 mm radius and 7 km length are lying at the site owing to several obstacles in completing the task. Meanwhile, the MSEDCL company has started to relocate the electric poles coming in the way and this work will be completed by July 31.”

“11 out of 53 ESRs were listed to be constructed on top priority. Out of which, the construction of ESRs at Hanuman Tekdi and Rauza Baugh-Himayat Baugh has been completed. The work of TV Center ESR is in progress. Meanwhile, the contractor has said that the works of 11 ESRs would be completed by October,” said Kazi.

Need of repairing roads

The internal distribution pipeline of length 1911 km will be laid down in the city, out of which, the laying of 490 km has been completed. There are complaints from the citizens that the roads are not being repaired after digging and completing the task of laying the pipelines. It is the responsibility of the contractor to make these roads as they were before and the CSMC will get the work done from him, he stressed.

Tags: MJPMJP AjaysinhaChhatrapati Sambhajinagar Municipal CorporationAnti-Encroachment Squad of Chhatrapati Sambhajinagar Municipal CorporationLokmat news network chhatrapati sambhajinagar the chhatrapati sambhajinagar municipal corporationChhatrapati sambhajinagar chhatrapati sambhajinagar municipal corporationSmart Schools of Chhatrapati Sambhajinagar Municipal CorporationAnti Encroachment Squad of Chhatrapati Sambhajinagar Municipal CorporationLokmat news network chhatrapati sambhajinagar chhatrapati sambhajinagar municipal corporationChhatrapati Sambhajinagar Municipal Corporation G SreekanthMunicipal CorporationHigh Court
Open in App

Related Stories

MumbaiBMC Election 2026: BJP to Contest On 137 Seats and Shiv Sena on 90 Seats

PunePune: Jolt to Shiv Sena (UBT) as Key Leaders Join BJP Ahead of PMC Elections

MumbaiMira-Bhayandar Municipal Corporation Elections: Uproar Over Voter List Errors at MBMC Review Meeting

NationalMadhya Pradesh High Court Grants Divorce to Man, Says False Allegations and Humiliation by Wife Are Mental Cruelty

EntertainmentShilpa Shetty Denies Receiving ₹15 Crore, Threatens Legal Action Over Defamation

Aurangabad Realted Stories

AurangabadSparkling Christmas cheer at Sapling School

AurangabadJoshua wins inaugural best student project award at NVS initiative

AurangabadUSF city chapter conducts 2-day residential camp

AurangabadMajor parties file nominations ahead of CSN elections

AurangabadAspirants gather in front of Jaleel's office