NHPC Ltd on Friday entered into a definitive agreement with lenders for the takeover of insolvent Lanco Teesta Hydro Power Ltd (LTHPL), which is implementing the 500 MW Teesta VI Hydropower project in Sikkim.

Open in App

Under the terms of the agreement, NHPC will be taking over 30 per cent equity in LTHPL and complete the power project being developed on Teesta river. The state-owned hydro power major has offered Rs 897.50 crore towards the resolution of LTHPL under the corporate insolvency resolution process.

NHPC already has operational projects upstream of the river and the addition of Teesta VI would give it almost full control of the river system in Sikkim. The company has been on the lookout for revivable hydro power projects facing insolvency proceedings as part of its plan to expand capacity.

NHPC has not got a project in the last 15 years. This is going to be the first project to commence construction after a gap of 15 years.

The LTHPL project will be implemented at an estimated project cost of Rs 5,748.04 crore (at July 2018 price level), which includes a bid amount of Rs 897.50 crore for acquisition. All creditors whose claims were admitted by the resolution professional will be getting 36 per cent of their claims on a pro-rata basis from the proceeds coming out of NHPC's bid.

Earlier in March 2019, the Cabinet Committee on Economic Affairs (CCEA) had approved the proposal for the acquisition. Later in July, the National Company Law Tribunal's (NCLT), Hyderabad bench approved the resolution plan of NHPC. LTHPL project will be completed in a period of five years.

"We tried to salvage the project and bid aggressively as there was an auction process. It is a a process which we have completed," NHPC Ltd Chairman and Managing Director o Balraj Joshi said at an event to mark the signing of this definitive agreement.

Joshi also said that NHPC would be bidding for the 120 MW Jal Power Project, another asset under the Insolvency and Bankruptcy Code.

For the Teesta VI, banks have also agreed to relax the payment schedules so that the process does not come under stress again. The levelised tariff from this project is estimated to be Rs 4.07 per unit.

( With inputs from IANS )

Tags: Nhpc LtdCabinet Committee On Economic Affairs
Open in App

Related Stories

NationalGovernment Announces New MSP for Rabi Crops: Wheat, Lentil, Mustard See Substantial Hikes

MumbaiMumbai-Indore Train Project: Cabinet Approves 309 Km Railway Line to Be Completed by 2028

PoliticsAssam govt employees to serve in 'difficult' areas

InternationalEAM Jaishankar reaches Zanzibar to deepen ties with Tanzania

PoliticsUCC necessary to bring uniformity, harmony: Khattar

कारोबार Realted Stories

BusinessCentre holds high-level meeting to strengthen energy security in Tamil Nadu

Business"Good, if data used for effective policy making," Acharya Prashant calls for using caste census for affirmative action

BusinessRBI panel suggests extending call money market timings to 7 p.m.

BusinessIllicit Trade Index: Pakistan loses Rs 3.4 trillion annually due to smuggling

BusinessIndia, Denmark sign pact to accelerate drive for clean energy