Most hydel, thermal power projects wallowing in time overruns

By IANS | Published: September 18, 2022 8:39 AM

New Delhi, Sep 18 As many as 12 out of 13 hydro projects and 30 out of 34 ...

Open in App

New Delhi, Sep 18 As many as 12 out of 13 hydro projects and 30 out of 34 thermal power projects are delayed in their execution, mainly due to issues like land acquisition and contractual inadequacies.

Most significantly, the 12 delayed hydro projects have a cumulative time overrun of 1,205 months or more than 100 years. The cost overrun in these projects has been Rs 31,530 crore, according to sources.

Similarly, due to the delay in execution of 30 thermal power projects out of 34, the time overrun has been 1,776 months or 148 years, while the cost overrun is Rs 41,100 crore.

Apart from delay in land acquisition and contractual shortcomings, the other issues which have contributed to the delay in completion of these hydro and thermal projects are disputes arising due to poor cost estimation of these projects, inadequate cost management, lack of funds and shortage in budget allocation, as well as poor site supervision by the contractors, sources privy to the development said.

Power sector experts point out that contract related disputes lead to delay in such big ticket projects, which can be avoided if proper planning and due diligence is conducted at the preliminary stages itself.

Also lack of strict norms and penalty imposition for completing various levels of activities in contractual agreements, leads to a lax attitude of contractors due to which work on such projects suffers.

The Ministry of Power, on its part, says that it has set up a dispute avoidance mechanism to avoid disputes between public sector undertakings (PSUs) and contractors related to hydro sector contracts at the inception stages.

However, official sources accepted the fact that due to lack of introduction and implementation of these measures earlier, led to the delays in several hydro and thermal projects.

Nevertheless, they informed that to avoid any further delay in such big projects, various corrective measures are being incorporated now.

The ministry has notified the November 2019 guidelines to reduce instances of time and cost overruns in hydro projects. These include preparation of realistic project schedule based on past experience.

Also with the help of latest software tools, projects are monitored on regular basis, ministry official said, adding that prior approval of competent authority is also sought if the project is not likely to be commissioned within the prescribed time limit.

NTPC conducts pre-bid conference with prospective bidders for major thermal projects, covering all technical and commercial aspects of the contract's terms and conditions, sources added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: ntpcMinistry Of PowerUnion ministry of powerUnion power ministryPower ministry of india
Open in App

Related Stories

NationalUnion Power Minister R. K. Singh Warns Against State Debt Amid Free Electricity Schemes

NationalOdisha: Fire Breaks Out at NTPC Talcher Kaniha Thermal Power Station in Angul (Watch Video)

BusinessPower availability rose to 22.30 hrs in rural areas, 23.3 hrs urban since 2014: RK Singh

NationalCentre issues guidelines for resource adequacy planning framework for power sector

NationalConsumers can save upto 20 pc in electricity bills with new power tariff rule

International Realted Stories

InternationalUS President's son Hunter Biden convicted in firearms case

InternationalPakistan's Economic Survey reveals major increase in donkey population

InternationalIsraeli soldiers share chilling experiences of October 7 terror attack amid ongoing war

InternationalAt least 49 dead, 140 missing after boat carrying refugees, migrants from Horn of Africa to Yemen sinks

InternationalJapan-India maritime exercise 'Jimex 24' commences in Japan