Chennai Metro rail steps up flood preparedness as northeast monsoon intensifies

By IANS | Updated: October 22, 2025 09:30 IST

Chennai, Oct 22 With the northeast monsoon bringing heavy rainfall across the region, the Chennai Metro Rail Limited ...

Open in App

Chennai, Oct 22 With the northeast monsoon bringing heavy rainfall across the region, the Chennai Metro Rail Limited (CMRL) has drawn up a comprehensive flood-mitigation plan to protect both its operational network and ongoing construction sites.

The initiative aims to prevent waterlogging at key metro stations and safeguard expensive tunnelling machinery used for Phase-2 expansion.

According to CMRL officials, vulnerable stations in Phase-1 and its extension -- including Government Estate, Saidapet, Teynampet, St. Thomas Mount, Koyambedu, Arumbakkam, Tiruvottiyur, and Toll Gate -- have been prioritised for enhanced flood protection measures.

Over 1,000 gunny bags, 300 cement blocks, and 20 fifty-kilogram cement bags have already been stocked at these sites to prevent seepage and flooding.

T. Archunan, Director (Projects), CMRL, said the agency has categorised its flood-preparedness efforts into four areas -- operational stations, under-construction sites, vulnerable locations such as OMR and Porur junction, and coordination with line departments like the Greater Chennai Corporation (GCC).

“We have plans to mitigate flooding in all categories of sites. Operational stations have been equipped with necessary materials, and construction zones are being secured with retaining walls and pumping systems. Coordination with GCC ensures rapid response in case of urban flooding,” he said.

At present, tunnelling operations using Tunnel Boring Machines (TBMs) and work on retrieving and launching shafts are in progress at several underground locations.

Heavy-duty pumps have been deployed to prevent water ingress that could potentially damage machinery and lead to significant financial losses.

In addition, CMRL has stationed 603 water pumps of various capacities across its Phase-2 corridors to continuously monitor and dewater flooded zones.

The deployment covers all three major corridors -- Corridor-3: Madhavaram Milk Colony to Siruseri-SIPCOT; Corridor-4: Lighthouse to Poonamallee Depot; Corridor-5: Madhavaram Milk Colony to Sholinganallur.

Officials said the Metro’s flood-response units are on round-the-clock alert, working closely with civic agencies to ensure seamless operation even during heavy downpours.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

InternationalUN chief seeks urgent action against global warming, urges countries to "fight misinformation" on climate

NagpurCPS (AB) paddlers win bronze

NationalAssam Rifles foil multiple insurgent attempts in NE

Other SportsFrench Open Badminton: Unnati Hooda advances to pre-quarters; Ayush Shetty makes early exit

BusinessRailways to run 1,500 extra trains in next 5 days to clear Chhath festive rush

National Realted Stories

NationalRailways to run 1,500 extra trains in next 5 days to clear Chhath festive rush

NationalSiddaramaiah ruined K’taka’s economy, claims Union Minister

NationalNC will win all 4 Rajya Sabha seats in J&K, says Omar Abdullah

NationalBengal Minister again appears before ED in teachers recruitment case

NationalJEEVIKA Didis place their trust in Nitish Kumar over Tejashwi Yadav