City
Epaper

Gujarat portion of Mumbai-Ahmedabad bullet train project to be completed by Dec 2027: Vaishnaw

By IANS | Updated: July 23, 2025 15:14 IST

New Delhi, July 23 The Gujarat portion of the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project between Vapi and ...

Open in App

New Delhi, July 23 The Gujarat portion of the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project between Vapi and Sabarmati is planned to be completed by December 2027, while the entire 508 km project is expected to be completed by December 2029, Railways Minister Ashwini Vaishnaw informed Parliament on Wednesday.

However, the bullet train project is a very complex and technology-intensive and the exact timelines for its completion can only be reasonably ascertained after the completion of all associated works of civil structures, track, electrical, signalling & telecommunication and supply of trainsets, the minister added.

MAHSR is under execution with technical and financial assistance from the Japanese government. The project is passing through Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad, and Sabarmati, the minister said.

A cumulative financial expenditure of Rs 78,839 crore has been incurred on the project till June 30, 2025, he said.

The total estimated cost of the MAHSR project is approximately Rs 1,08,000 crore, out of which Japan International Cooperation Agency (JICA) is funding 81 per cent of the project cost which works out to Rs 88,000 crore while the balance 19 per cent cost amounting to Rs 20,000 crore will be funded through equity contribution from Ministry of Railways (50 per cent) and Maharashtra and Gujarat state governments (25 per cent each).

The delay in land acquisition in Maharashtra impacted the project till 2021. However, currently, the entire land (1389.5 hectares) for the MAHSR project has been acquired. The Final Location Survey and Geotechnical investigation has also been completed, and alignment finalised. All Statutory Clearances relating to wildlife, Coastal Regulation Zone (CRZ) and Forest clearance have been obtained, and all the civil contracts of the project have been awarded, Vaishnaw said.

Till now, 392 km of pier construction, 329 km of girder casting and 308 km of girder launching have been completed. The work on the undersea tunnel (21 km approx.) has also started. In order to expand the high-speed rail (HSR) network in India beyond the MAHSR corridor and to meet the growing passenger demand between major cities of commercial and tourist importance, Detailed Project Reports (DPRs) are being prepared by the National High Speed Rail Corporation Limited (NHSRCL), he added.

HSR projects are highly capital-intensive, and any decision to take up a new project is based on many factors such as technical feasibility, financial & economic viability, traffic demand and availability of funds & financing options. The commercial operation of the MAHSR project involves an affordable fare structure for the services, taking into account the socio-economic conditions of the clientele for optimum patronage of the HSR sectors, the minister added.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

InternationalPresidential office welcomes Trump's approval of South Korea's nuclear-powered submarine bid

InternationalSouth Korean Lee, Canadian PM agree to bolster defence, security partnership

InternationalJapan's Takaichi arrives in South Korea, set for summit talks with Lee

InternationalBaloch human rights body terms jail trial of its leaders, activists 'political revenge'

TechnologyIIT Madras aces vertical take-off and landing in aircraft, UAVs with hybrid rocket thrusters

Technology Realted Stories

TechnologyChina targets manned moon landing by 2030, outlines testing tasks ahead

TechnologyAdding more women in STEM sectors imperative for Viksit Bharat vision

TechnologyHyundai Motor's Q3 net profit falls 20.5 pc on US tariffs

TechnologyCity doctors report 50 pc rise in eye problems as smog continues to engulf Delhi

TechnologyAI-171 crash: Preliminary report finds no fault in Air India’s operations, says CEO Campbell Wilson