India, Nepal hold Joint Working Group meeting on cross border railway links

By ANI | Published: October 08, 2021 11:46 AM

India and Nepal held the 5th Joint Working Group (JWG) and the 7th Project Steering Committee (PSC) meetings from 6-7 October 2021 in New Delhi, to review the implementation of ongoing cross-border railway links and overall bilateral cooperation in the railway sector.

Open in App

India and Nepal held the 5th Joint Working Group (JWG) and the 7th Project Steering Committee (PSC) meetings from 6-7 October 2021 in New Delhi, to review the implementation of ongoing cross-border railway links and overall bilateral cooperation in the railway sector.

A Ministry of External Affairs (MEA) release said that both sides signed the Standard Operating Procedures (SOPs) for the start of passenger train services on the Jaynagar-Kurtha section and the Memorandum of Understanding (MoU) for Final Location Survey (FLS) of the proposed broad gauge railway line between Raxaul and Kathmandu.

The SOPs provide the technical aspects of running passenger trains on the new section and will serve as a guiding document for the early start of rail services in the upcoming cross-border railway links with Nepal. The proposed Raxaul-Kathmandu broad gauge railway line will further boost connectivity between India and Nepal, the release said.

Both sides discussed the ongoing works of Jaynagar-Bijalpura-Bardibas and Jogbani-Biratnagar broad gauge railway lines between India and Nepal, being developed with grant assistance from the Government of India. The technical preparedness of the completed 34 km long section of the railway line, from Jaynagar (India) to Kurtha (Nepal) for the operationalization of passenger train services was also reviewed.

The Nepali side also informed that a necessary regulatory framework will be put in place to facilitate early operationalization. For Kurtha to Bilajpura (17.25 km) section of the railway line, the Nepal side assured to provide necessary facilitation for completion of the work at the earliest. Both sides also agreed to expedite the work on completion of the 18.6 km long Jogbani-Biratnagar rail link, and its early operationalization, MEA said.

The progress on Raxaul-Kathmandu Broad Gauge Railway Link and Phase-II railway link projects were also discussed. Both sides agreed to enhance technical cooperation in the railway sector, including in the areas of capacity building, logistic support and training of Nepali railway personnel.

( With inputs from ANI )

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: 5th joint working groupProject steering committeeNew DelhiRaxaulThe new delhi municipal councilDelhi south-west
Open in App

Related Stories

NationalFire Breaks Out in Delhi House, Four Vehicles Gutted in Blaze

MaharashtraBhima-Koregaon Case: Supreme Court Grants Bail to Gautam Navlakha in Elgar Parishad Case After Two Years of House Arrest

NationalNew Delhi: 30-Year-Old Man Arrested for Demanding Rs 20 Lakh From Car Showroom Owner

NationalNew Delhi: 28-Year-Old Man Held for Molesting Minor Boy in Metro

InternationalCBI Arrests 4 for Trafficking Indians Into Russia-Ukraine Conflict Zone (See Tweet)

International Realted Stories

InternationalChina's cyberattacks on Taiwan surges ahead of presidential inauguration

InternationalLadakh announces second edition of 'land art exhibition' from June 1

InternationalDubai Ruler meets with Prime Minister of Kuwait on sidelines of 33rd Arab League Summit

InternationalPM Keith Rowley of Trinidad and Tobago meets Maharashtra Governor at Raj Bhavan in Mumbai

InternationalUAE President receives phone call from President of Brazil; orders urgent relief aid for flood victims