City
Epaper

MMRDA completes 73% work of pillars for 6 Mumbai Metro lines

By IANS | Updated: July 6, 2023 20:00 IST

Mumbai, July 6 The Mumbai Metropolitan Regional Development Authority (MMRDA) has said that it has erected 3,603 out ...

Open in App

Mumbai, July 6 The Mumbai Metropolitan Regional Development Authority (MMRDA) has said that it has erected 3,603 out of 4,929 pillars -- or 73 per cent of the work -- on the upcoming 6 new Mumbai Metro lines in the Mumbai Metropolitan Region (MMR), here on Thursday. 

These include the Metro 2B (D.N. Nagar-Mandale) 614 out of 1,109 pillars or 50.70 per cent; Metro 4 and 4A (Wadala-Kasarvadavali) 973 out of 1,476 and 143 out of 221 respectively, or 55 per cent completion.

Metro 5 Phase I (Thane-Bhiwandi) 440 out of 464 pillars or 78.40 per cent done; Metro 6 (Swami Samarth Nagar-Vikhroli) 657 out of 768 or 70.75 per cent completed; and Metro 9 (Dahisar-Mira Bhayander) 776 out of 900 or 61.28 per cent done.

This was despite the major challenges of construction activities in a congested city with heavy traffic and care was taken to do most activities during the night time.

During the construction process, the focus was on the casting and erection of heavy-weight precast elements, such as pier caps, U-girders, and I-girders which are produced at different casting yards, transported to the location during the night time.

There, they are erected at specific sites using cranes with capacities ranging from 350 MT to 500 MT.

"We are prioritising the completion of all Mumbai Metro corridors as quickly as possible. The recently inaugurated Metro Lines 2A and 7 are providing relief to lakhs of commuters, contributing to reduced highway traffic plus air and noise pollution," said MMRDA Metropolitan Commissioner Sanjay Mukherjee.

He said that the MMRDA is in the process of appointing a consultant to obtain various permissions for the Metro 10 between Gaimukh and Shivaji Chowk (Mira Road in Thane district), plus a general consultant for the tendering process and other formalities for the planned Metro Line 12 (Kalyan-Taloja, in Thane district).

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Mumbai metropolitan regional development authorityMMRSanjay mukherjeeMmr & puneMmr real estateMmr real estate market remains
Open in App

Related Stories

MumbaiMumbai Metro News: Automated Train Wash, 64 Stabling Lines Planned at Mogharpada in Thane

MumbaiMaharashtra Forms Special Task Force to Integrate MMR Bus Services After Mumbra Train Tragedy

ThaneMaharashtra Deputy CM Eknath Shinde Sets Deadline for Delayed Kalu Dam Project to Tackle Water Woes in Thane Region

Navi MumbaiNavi Mumbai Parking Policy in Final Stage, Proposal to Be Sent for State Govt Approval

MaharashtraCM Devendra Fadnavis Unveils Rs 4.07 Lakh Crore Investment Plan to Transform Mumbai Region

Politics Realted Stories

MaharashtraNCP Leader Suraj Chavan Shares Alleged Black Magic Video of Shiv Sena Leader Bharat Gogawle Amid Row Over Raigad Guardian Post

MaharashtraMaharashtra Politics: Raj Thackeray Meets CM Devendra Fadnavis at Taj Lands End Amid Rumours of MNS–Sena UBT Alliance

MaharashtraMaharashtra Municipal Elections 2025: Mahayuti Alliance to Contest Civic Body Polls Together, Says CM Devendra Fadnavis

Maharashtra'Remembered the Advice My Mother Gave Me': Supriya Sule On Her WhatsApp Status

Maharashtra'Will Give News Soon': Uddhav Thackeray's Big Statement on Possible Alliance of Shiv Sena UBT and MNS