City
Epaper

Storage-backed renewable energy capacity in India to surge past 25 GW in 3 years

By IANS | Updated: May 14, 2025 15:07 IST

New Delhi, May 14 Installed capacity of storage-backed renewable energy (RE) in India is likely to increase to ...

Open in App

New Delhi, May 14 Installed capacity of storage-backed renewable energy (RE) in India is likely to increase to 25-30 gigawatt (GW) by financial year 2027-28 from almost zero during 2024-25, according to a Crisil Ratings report released on Wednesday.

The incremental capacity will account for more than 20 per cent of the total RE capacity to be added over the three years, driven by the central government’s push to make renewables more sustainable, the report added.

Storage-backed RE projects provide an effective solution for the intermittent nature of RE generation. Such projects -- which include firm and dispatchable renewable energy, solar with energy storage, etc --supply power when required, supporting grid stability. For instance, these can provide green power on a monthly or hourly schedule or at the peak hours of morning and evening.

The government is pushing for these projects in a bid to make renewables a sustainable part of the country’s power mix. The thrust is reflected in the high volume of these projects in recent tender auctions, forming around 25 per cent (or 11 GW) of the total capacity awarded through tenders by central agencies in calendar year 2024 as against 11 per cent (or 2.5 GW) in calendar year 2023. Given the high energy requirements, these projects need an average oversizing to the extent of 2.5 times of contracted capacity. This has resulted in a cumulative capacity pipeline of around 34 GW.

However, almost the entire capacity awarded through these tenders is either in development or in a nascent stage of construction, which exposes these to risks inherent in project implementation.

Risks in these projects typically manifest in the form of delay in securing offtake agreements, funding and execution. But we believe these risks to commissioning with material overruns would be low to moderate -- with off-take and funding risks being low. Further, the proactive approach by developers, especially towards land and connectivity requirements, augurs well -- limiting the construction risks.

Offtake risk is low for nearly half of the upcoming capacity as these have secured long-term (25 years) power purchase agreements (PPAs) at a fixed tariff, which also provides revenue visibility. For the remaining half, the risk is elevated as their tariffs are 55 per cent higher compared with vanilla RE projects, which could delay signing of PPAs.

"However, there are at least three reasons to believe these projects, too, will tie up PPAs in the near term -- first, the government’s push for a higher share of green power in overall energy generation; second, increased ability of these projects to meet higher energy requirements (akin to thermal plants) at tariffs; and third, increasing renewable purchase obligations (RPO) of discoms," the report mentioned.

Funding availability is also not expected to be a material challenge as the healthy cash-flow generation potential post commissioning (backed by higher generation profile and tariffs) as well as long-term revenue visibility through 25-year PPAs should spur lender interest, according to the report.

Ankush Tyagi, Associate Director, Crisil Ratings, said that “finally, execution risks related to construction appear low to moderate".

"Based on our understanding from developers, nearly 70 per cent of the awarded capacities in calendar year 2024 have either identified or secured the critical resources required -- mainly land and grid connectivity -- prior to bid participation. This will stand them in good stead," he added.

However, material challenges pertaining to timely receipt of land and evacuation infrastructure as well as delayed PPA closure against our base expectation could result in longer-than-anticipated execution timelines and will bear watching, the report noted.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

InternationalChinese envoy highlights 10 points of consensus in talks between India, China SRs on boundary question

InternationalIndia rejects Nepal's objection to Lipulekh trade agreement with China, calls territorial claims "untenable"

InternationalNepal objects agreement of India-China to open trade route via Lipulekh, asserting its claim

MumbaiMumbai: Nepali Couple Arrested at CSMI Airport for Travelling with Forged Indian IDs

NationalCentre allows Tripura to certify paddy seeds for Manipur, Mizoram: Minister

Technology Realted Stories

TechnologyIndia successfully test-fires Agni-5 ballistic missile, validates strategic capabilities

TechnologyAdvanced therapies, tech key to tackle rare disease burden in India: CDSCO, NITI Aayog

TechnologyGaming worse than drugs, several lost lives after savings wiped out: Ashwini Vaishnaw

TechnologyIndia’s workforce goes AI-first as frontier firms lead transformation: Report

TechnologyEurope sets new records for mosquito-borne West Nile virus, chikungunya disease: ECDC