Road work in Chikalthana industrial area hits roadblock

By Lokmat English Desk | Updated: September 6, 2023 19:40 IST

Four months have passed since the tenders were finalisedChhatrapati Sambhajinagar: The long-awaited road repair work in Chikalthana MIDC, ...

Open in App

Four months have passed since the tenders were finalised

Chhatrapati Sambhajinagar: The long-awaited road repair work in Chikalthana MIDC, has hit a roadblock, causing distress among local entrepreneurs. The industry minister, Uday Samant, had inaugurated the road work with a foundation stone-laying ceremony on April 25. However, despite nearly four months passing since the tender was finalized, the contractor appointed, and other administrative matters settled, the repair work has yet to be completed.

The then guardian minister, Subhash Desai had issued an order to Maharashtra Industrial Development Corporation (MIDC) to propose a road construction plan. Unfortunately, due to a lack of coordination between MIDC and the municipal corporation, no consensus was reached on the proposal, and complications arose over service charges.

In a bid to revive the stagnant project, minister Samant visited Chhatrapati Sambhajinagar on October 21, 2022, during which the road conditions in Chikalthana MIDC were discussed during a review meeting with local entrepreneurs. Following the meeting, Samant directed MIDC officials to submit revised proposals. A budget of Rs 53 crores was sanctioned for the enhancement, repair, and renovation of 36 kilometers of roads in the industrial estate.

Worry about disruption of underground cables

Further complicating the situation is the necessity for careful coordination during the roadworks, as water lines, electric lines, and cables are situated beneath the roads, posing a risk of disruption to industrial operations if damaged. Entrepreneurs are now calling for a coordination meeting involving MIDC and other relevant stakeholders to ensure a smooth and trouble-free road repair process.

Proposal of 50 percent share left pending

During the resolution of these development issues within the municipal limits, MIDC proposed a revenue-sharing arrangement, suggesting that 50 percent of the property tax should be allocated to them, with the remaining 50 percent going to the municipal corporation. But this proposal failed to secure approval from the corporation, and the matter was left pending, particularly after a change in government.

Open in App

Related Stories

NationalKarnataka BJP expels leader for inappropriate behaviour against woman

NationalShiv Sena accuses UBT faction MPs of spreading misinformation about Army; seeks investigation

International"Stopped a nuclear conflict", says Trump as he claims to have brokered India-Pak peace

TechnologyUPI Down: Google Pay, Paytm Users Face Transaction Failures On Mobile

HealthReset blood test reference values to suit Indian conditions: Scientist

Aurangabad Realted Stories

AurangabadViolence in religion’s name is against its principles: Dr Ram Puniyani

AurangabadSSC result to be out today

AurangabadToday’s parenting: Building foundation for a child’s emotional world

AurangabadCultural Festival in Delhi on Sambhaji Maharaj Jayanti

AurangabadCopper wire worth ₹5 lakh stolen from hardware shop