PM Modi reviews progress of bullet train corridor during visit to Surat

By IANS | Updated: November 15, 2025 15:00 IST

Surat, Nov 15 Prime Minister Narendra Modi on Saturday undertook a detailed review of the Mumbai–Ahmedabad High-Speed Rail ...

Open in App

Surat, Nov 15 Prime Minister Narendra Modi on Saturday undertook a detailed review of the Mumbai–Ahmedabad High-Speed Rail (MAHSR) project during his visit to Gujarat, marking a key moment in India’s push towards next-generation transport infrastructure.

Arriving at Surat International Airport on Saturday morning, the Prime Minister proceeded by helicopter to Antroli, where the under-construction Surat Bullet Train Station — one of the flagship stations of the corridor — is taking shape.

During the visit, the Prime Minister inspected the Surat station — a structure inspired by the city’s globally renowned diamond industry.

With a height of 26.3 metres and a built-up area of 58,352 sq.mt, the station includes three levels: The ground floor for parking and security checks, the concourse level for lounges, restrooms, kiosks and ticketing, and the platform level for passenger boarding.

While structural work is complete, finishing touches such as interiors and station amenities are currently underway. Track works, including RC track-bed construction and temporary track installation, have also been completed at the site.

The visit focussed on assessing the progress of India’s first Bullet Train project, spanning 508 kms between Mumbai and Ahmedabad. Of this, 352 km lies in Gujarat and Dadra & Nagar Haveli, and 156 km in Maharashtra.

The corridor will connect major cities such as Ahmedabad, Vadodara, Bharuch, Surat, Vapi, Thane and Mumbai, and is expected to cut travel time between the two metros to around two hours, significantly boosting inter-city mobility.

According to the National High-Speed Rail Corporation Ltd. (NHSRCL), over 85 per cent of the corridor —around 465 km — is being built on elevated viaducts, with 326 km already completed.

Progress on river bridges is also substantial, with 17 of 25 bridges constructed. The 47-km Surat–Bilimora section is among the most advanced stretches, where civil works and track-bed preparation have been fully completed.

The Prime Minister’s on-site review highlights the Centre’s emphasis on expediting large-scale, high-impact infrastructure projects. Once operational, the MAHSR corridor is expected to transform regional connectivity, accelerate economic development, and place India firmly among countries with advanced high-speed rail networks.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Open in App

Related Stories

CricketIPL 2026 Retention: Andre Russell Released by Kolkata Knight Riders Ahead of Auction

TechnologyIndian biosphere reserves testament to how culture, sustainable development can coexist

LifestyleOshea Herbals’ Founder & CEO, Mr. Jeetendra Kundlia, Felicitated at ABP Ananda GST Conclave 2025 in Kolkata

BusinessIndian biosphere reserves testament to how culture, sustainable development can coexist

BusinessOshea Herbals’ Founder & CEO, Mr. Jeetendra Kundlia, Felicitated at ABP Ananda GST Conclave 2025 in Kolkata

National Realted Stories

NationalIndian biosphere reserves testament to how culture, sustainable development can coexist

NationalPoll debacle: RJD will continue to 'serve' poor, VIP's Mukesh Sahani accepts public mandate

NationalEPS, Annamalai slam TN govt after South Korean firm shifts to Andhra Pradesh

NationalRed Fort blast: Delhi Police tighten grip on Al Falah University, file two FIRs

NationalKerala Travel Mart Society warns tourists of rising online hotel booking frauds