Controlled blasting begins in Jayakwadi

By Lokmat English Desk | Updated: January 13, 2024 22:15 IST

Chhatrapati Sambhajinagar: Controlled blasting started in Jayakwadi dam. Blasting will have to be done up to six meters. This ...

Open in App

Chhatrapati Sambhajinagar: Controlled blasting started in Jayakwadi dam. Blasting will have to be done up to six meters. This work will take one month. The target of setting up a jackwell i.e. water pumping station for the new water supply scheme by the end of December has been kept in mind.

Excavation up to 19 meters will be done in the dam for jackwell. After 13 meters the work was stopped due to black rock. Control blasting was allowed by the water resources department. GVPR company chief officer Mahendra G said that blasting has been started. Blasting is being done by drilling holes in the black rock. This work will be done in two phases. The blasting work will be completed by February 15, after which the main work of jackwell will be started.

Open in App

Related Stories

InternationalIndia asks X to ban over 8k accounts subject to penalties

National24 airports shut, airlines issue travel advisories amid tensions between India-Pakistan

NationalIndia to present its case today before IMF to review bailout package to Pakistan

InternationalAttack on India "will be met with a very very firm response", EAM says

InternationalIndia to present its case today before IMF to review bailout package to Pakistan

Aurangabad Realted Stories

AurangabadBalancing scales: Judicial independence and accountability in India

AurangabadHP fuel supply disruption resolved after 24-hour halt

Aurangabad"Investigate Sukre, reinstate Rathod – Jaiswal"

AurangabadNo change in most of school uniforms

AurangabadThat strange taste in your water?