MMRDA completes 73% work of pillars for 6 Mumbai Metro lines

By IANS | Published: July 06, 2023 7:58 PM

Mumbai, July 6 The Mumbai Metropolitan Regional Development Authority (MMRDA) has said that it has erected 3,603 out ...

Open in App

Mumbai, July 6 The Mumbai Metropolitan Regional Development Authority (MMRDA) has said that it has erected 3,603 out of 4,929 pillars -- or 73 per cent of the work -- on the upcoming 6 new Mumbai Metro lines in the Mumbai Metropolitan Region (MMR), here on Thursday. 

These include the Metro 2B (D.N. Nagar-Mandale) 614 out of 1,109 pillars or 50.70 per cent; Metro 4 and 4A (Wadala-Kasarvadavali) 973 out of 1,476 and 143 out of 221 respectively, or 55 per cent completion.

Metro 5 Phase I (Thane-Bhiwandi) 440 out of 464 pillars or 78.40 per cent done; Metro 6 (Swami Samarth Nagar-Vikhroli) 657 out of 768 or 70.75 per cent completed; and Metro 9 (Dahisar-Mira Bhayander) 776 out of 900 or 61.28 per cent done.

This was despite the major challenges of construction activities in a congested city with heavy traffic and care was taken to do most activities during the night time.

During the construction process, the focus was on the casting and erection of heavy-weight precast elements, such as pier caps, U-girders, and I-girders which are produced at different casting yards, transported to the location during the night time.

There, they are erected at specific sites using cranes with capacities ranging from 350 MT to 500 MT.

"We are prioritising the completion of all Mumbai Metro corridors as quickly as possible. The recently inaugurated Metro Lines 2A and 7 are providing relief to lakhs of commuters, contributing to reduced highway traffic plus air and noise pollution," said MMRDA Metropolitan Commissioner Sanjay Mukherjee.

He said that the MMRDA is in the process of appointing a consultant to obtain various permissions for the Metro 10 between Gaimukh and Shivaji Chowk (Mira Road in Thane district), plus a general consultant for the tendering process and other formalities for the planned Metro Line 12 (Kalyan-Taloja, in Thane district).

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: Mumbai metropolitan regional development authorityMMRSanjay mukherjeeMmr & puneMmr real estateMmr real estate market remains
Open in App

Related Stories

MaharashtraHeat Wave Grips Mumbai: PAWS Organization Steps Up to Aid Stray Animals Amid Rising Temperatures

BusinessChandak Group brings back the charm of homes of the olden days

NationalNCB busts major drug trafficking syndicate in Mumbai's Dongri, 20 kg of mephedrone worth over Rs 1 cr seized

MaharashtraSanjay Mukherjee appointed MMRDA commissioner

MaharashtraMaharashtra govt likely to remove property tax for flats up to 500 sq ft in Navi Mumbai

Politics Realted Stories

PoliticsPM Modi Reacts to Potential NCP (SP) Merger with Congress: Is Sharad Pawar Nervous about Baramati?

PoliticsArvind Kejriwal Counters PM Modi’s Critique of AAP Scheme, says “Why Can’t Women Get Free Bus Rides When....?"

Politics"Whatever I Have Learnt In Politics Has Been Taught By Amethi’s People": Rahul Gandhi

PoliticsExclusive Interview of PM Narendra Modi to Rishi Darda: Congress’ Shahzada Speaking Language of Maoists

PoliticsLok Sabha Election 2024: People of Maharashtra Have Been Greatly Supportive of the NDA, Says Prime Minister Narendra Modi