Main coolant pipeline for third atomic power plant at Kudankulam completed

By IANS | Updated: August 11, 2023 16:30 IST

Chennai, Aug 11 The welding of the main coolant pipeline at the upcoming third 1,000 MW atomic power ...

Open in App

Chennai, Aug 11 The welding of the main coolant pipeline at the upcoming third 1,000 MW atomic power plant at Tamil Nadu's Kudankulam got completed early this month, Russia’s integrated nuclear power major Rosatom said on Friday.

According to Rosatom, the welding of the main coolant pipeline which began in December 2022, was completed on August 5.

The main coolant pipeline combines the main equipment of the primary circuit, including the reactor, the steam generators, and the reactor coolant pumps. Considering high requirements for quality and operational conditions, the main coolant pipeline welding is one of the most complicated and important stages of civil and erection works at the power unit.

"It is the reactor coolant pipeline that carries the water heated in the reactor into the steam generators from which the generated steam goes into the turbine steam path, and the turbine generator generates electricity," Rosatom said.

The Russian company said the main coolant pipeline has a total length of about 140 m, the thickness of the pipe walls is 70 mm, and the total length of 28 welded joints is more than 87 m. Its design service life is 60 years in a tough environment.

During the welding of the main coolant pipeline which began in December 2022, a technology proposed by the Russian party was used, which made it possible for the Nuclear Power Corporation of India Ltd (NPCIL) to reduce the operation time from 270 to 219 days.

Upon completion of the main coolant pipeline welding, "flushing with the open reactor" operations and the "hydraulic tests and circulation flushing of the primary circuit" stage will start, Rosatom added.

India's atomic power plant operator NPCIL has two functional 1,000 MW plants (Units 1 and 2) at Kudankulam, while four more (Units 3, 4, 5 and 6) are under construction. All the six units are built with Russian technology and equipment supplied by Rosatom.

Major equipment for building the third and fourth units have reached Kudankulam from Russia, while a sizable number of components for the fifth and sixth units are to come.

Disclaimer: This post has been auto-published from an agency feed without any modifications to the text and has not been reviewed by an editor

Tags: congresspitrodadelhimodideepikabjpwest-bengaldeepika-padukoneajay-devgnthakur
Open in App

Related Stories

National“Shameful Display of Puppetry”: TMC’s Mahua Moitra Criticises Election Commission

NationalDelhi: Moti Nagar Woman Arrested for Filing False Murder Complaint; Police Investigate Past Allegations

NationalDelhi on Alert as Yamuna Crosses Danger Level, Authorities Issue Advisory

NationalDelhi Shocker: 24-year-old Man Stabbed To Death, Following Drunken Quarrel Over Money, Accused Arrested

NationalBJP Parliamentary Board To Meet on Aug 17, Discussion Likely on Vice Presidential Candidate

Technology Realted Stories

TechnologyInspiring to see young innovators as torchbearers of Atmanirbhar Bharat: Gautam Adani

TechnologyPakistan’s $5 billion investment in LNG infrastructure turns out to be a big fiasco

TechnologyWhatsApp rolls out call scheduling and new in-call tools

Technology'India is proud of your feat', says PM Modi to IAF Group Captain Shubhanshu Shukla

TechnologyGST reforms likely to boost auto, bank, cement stocks: Report