HCC completes 3.82 km tunnel for Mumbai Metro III

By IANS | Updated: August 2, 2019 16:00 IST

The Hindustan Construction Company (HCC) on Friday said that as part of the upcoming Mumbai Metro III project it had completed boring the first 3.82 km long tunnel passing underneath some of the most thickly populated areas of south Mumbai.

Open in App

Terming it "a challenging task", a company spokesperson said HCC has finished the south-bound tunnel between Chhatrapati Shivaji Maharaj Terminus (CSMT) and Mumbai Central stations, becoming the first contractor among all others to complete the entire length of a tunnel for the Metro III project.

The HCC maintained an average drilling rate of around 8.20 metres per day for the 3.82 km long tunnel passing via the station boxes of Kalbadevi, Girgaon and Grant Road.

This section is part of the 33.50 km long Metro III line connecting Colaba-Bandra-SEEPZ (Andheri East) and will be the first fully underground metro in the city. It is being built at a cost of around Rs 23,136 crore, with a Rs 13,325 crore loan from the Japan International Cooperation Agency (JICA).

The HCC teams encountered several geological and urban challenges, including proximity to the Arabian Sea, tunneling through heterogeneous reclaimed land, congested working areas and drilling below some of the oldest residential and other buildings, many over a century old, without disturbing their foundations.

The Mumbai Metro Rail Corporation Ltd (MMRCL) had awarded the contract to HCC in July 2016 for the design and construction of twin tunnels by Tunnel Boring Machines (TBM) and construction of four underground metro stations at CSMT, Kalbadevi, Girgaon and Grant Road.

For the work, HCC procured two TBMs from China with 117 metre long single-shield dual-mode hard rock with a 6.68 metre diameter and weighing 848 tonnes, the company said.

These TBMs are equipped to operate in both - open or closed - modes, in the predominantly fresh, and slightly to moderately weathered Basalt and Breccia that was anticipated in the Mumbai Metro projects.

After months of geotechnical investigations, planning and procurement processes, the first TBM, Vaitarna I, was launched at CSMT on December 4, 2017. Its initial drive was completed on January 11, 2018, while the main drive ended in mid-February 2018 with a team of 32 people working on it, the spokesperson said.

Since congested residential areas are located above the tunnel, structural surveys using sophisticated instruments were carried out prior to starting the boring work in a 30 metre influence zone on either side of the alignment to assess its impact on the buildings.

With the tunneling work completed well within the stipulated time, the HCC has now taken up the work of constructing the underground metro stations, each with a unique design.

( With inputs from IANS )

Tags: HCCmumbaiKalbadevi
Open in App

Related Stories

MumbaiMumbai Traffic Update: Police Issue Advisory for Shiv Sena UBT Dussehra Rally On October 2; Check Diversions

MumbaiMumbai: FIR Filed Over Maharashtra Congress’ Social Media Post Allegedly Inciting Violence

MumbaiMumbai: MNS Workers Protest at Andheri Metro Station, Damage Billboard, Demand Only Marathi Ads

MumbaiMumbai: Bomb Threat at Dadar Railway Station; Police Launch Investigation

MaharashtraMaharashtra Rains: Holiday Declared in All Schools in Palghar on September 29 Due to Heavy Rains

कारोबार Realted Stories

Business91 online govt services restored after data centre fire in S. Korea

BusinessCentre receives Rs 12.83 lakh crore in receipts up to August this fiscal

BusinessDedicated team within ICAR to conduct sugarcane research: Shivraj Singh Chouhan

BusinessCentre extends Unified Pension Scheme switch deadline till Nov 30

BusinessLPG connections in India have jumped to over 33 crore in last 11 years: Hardeep Puri