City
Epaper

Railway ministry claims more than 98 percent land acquired for bullet train project in Maharashtra

By Lokmat English Desk | Published: December 19, 2022 3:53 PM

Work on the railways' ambitious bullet train project between Mumbai and Ahmedabad has gained momentum, with the ministry claiming ...

Open in App

Work on the railways' ambitious bullet train project between Mumbai and Ahmedabad has gained momentum, with the ministry claiming that more than 98 per cent of the land has been acquired for the project in Maharashtra.

Piers have been erected for a distance of more than 118 kilometres, girders are being launched and the work on the construction of bullet train stations has also started, the railway ministry said.

With the change of government in Maharashtra, the pain points in the project in terms of forest clearances and land acquisition seem to have been overcome.

In a series of tweets, the ministry claimed that while 98.22 per cent land has been acquired in Maharashtra, in Gujarat, 98.87 per cent land has been acquired and in Dadra and Nagar Haveli, 100 per cent of the land has been acquired for the project.

The physical progress till November 23 was 24.1 per cent, the ministry said, adding that while almost 30 per cent of the work has been completed in Gujarat, in Maharashtra, around 13 per cent has so far been achieved.

The Mumbai-Ahmedabad bullet train project is of 508 km and most of it is in Gujarat. In Maharashtra, the National High Speed Rail Corporation Limited (NHSRCL), the implementing agency of the project, has to develop the Bandra-Kurla Complex and the network in Thane, Virar and Boisar.

The contract for the construction of a bullet train station at the Bandra-Kurla Complex and the one for the construction of an underground tunnel have also been allotted. Pier and girder works will soon be visible in Maharashtra like in Gujarat, officials said.

Tags: Railway Ministrybullet train projectmaharashtraAhmedabad
Open in App

Related Stories

PunePune Crime: Ex-Husband Murders Wife’s New Spouse, Woman Injured

NashikNashik's Water Crisis: Gangapur Dam at 8 %, Over 700 Tankers Deployed

NashikOld Nashik Residents Rally for Clean Water Amid Contamination Crisis

PoliticsShiv Sena (UBT) Claims Several Shinde Sena MLAs Seeking Re-entry; Outlines Condition for Accepting Rebels

NashikNashik: NMC Orders Immediate Halt To Road Digging Amid Monsoon Precautions

Maharashtra Realted Stories

MaharashtraBhiwandi's Transportation Woes: Damaged Bridges, Congested Roads and Maintenance Works Leave Residents Frustrated

MumbaiMumbai Stone Pelting: Over 50 Arrested After Violent Unrest in Powai During Anti-Encroachment Drive

MumbaiMumbai: BMC Promises To Fill Potholes Within 24 Hours of Receiving Complaints, Sets Up 72 Mastic Machines

PuneMahadev Betting App Case: Masterminds Among 94 Granted Bail

MumbaiMumbai Local Train Update: Services Disrupted on Western Line Between Nala Sopara and Virar