Worli-Sewri Connector Hits Roadblock as Elphinstone Chawl Redevelopment Stalls

By Lokmat English Desk | Updated: July 4, 2025 08:46 IST

With the monsoon in full swing, residents of 19 dilapidated chawls near Elphinstone Bridge in Prabhadevi are living in ...

Open in App

With the monsoon in full swing, residents of 19 dilapidated chawls near Elphinstone Bridge in Prabhadevi are living in fear and uncertainty. These structures are slated for demolition as part of the Worli-Sewri Connector project, but a delayed government order on their cluster redevelopment has left the project—and the people—hanging in limbo. The ₹1,286 crore, 4.5-kilometre-long connector is a major infrastructure project meant to link Worli to the upcoming Atal Setu in Sewri-Nhava Sheva. However, construction has come to a standstill due to issues surrounding the rehabilitation of affected residents. Although the state government approved a cluster redevelopment plan for the 19 chawls three months ago, the Urban Development Department has yet to designate an implementing authority.

 

Originally, 19 chawls and buildings in the Prabhadevi and Parel areas were to be cleared. But when the rehabilitation costs crossed ₹5,200 crore, the Mumbai Metropolitan Region Development Authority (MMRDA) revised the connector’s alignment. Only two chawls—Laxmi Nivas and Haji Noorani—along with the aging Elphinstone railway bridge were then marked for demolition, to be replaced with a double-decker structure.

 

Eighty-three families and shopkeepers from the two chawls were moved to transit camps and offered either alternate housing or compensation based on government ready reckoner rates. But many residents—some living in the area for decades—have refused to relocate, citing low compensation compared to the actual market value, which is nearly double.

 

Local residents have also opposed any relocation, demanding in-situ rehabilitation for all 19 chawls, given that construction activities will impact them all. This led to a high-level meeting chaired by Chief Minister Devendra Fadnavis in April, where it was decided that all 19 chawls would be redeveloped as a single cluster. But the delay in finalizing which agency will handle the redevelopment has brought progress to a halt.

 

With rains intensifying, residents of these crumbling chawls fear for their safety. Meanwhile, the incomplete connector remains stalled on both ends—at Worli and Sewri—awaiting the green light that could finally move the redevelopment and the infrastructure project forward.

Tags: Sewri-worli elevated corridorWorliSewriMumbai NewsMaharashtra NewsElphinstone Bridge
Open in App

Related Stories

MumbaiMumbai Local Train Robbery: Labourer Strangled With Belt, Rs 11,000 Stolen; 6 Arrested

PunePune Crime: 29-Year-Old Woman Robbed at Knife-Point in Koregaon Park Flat; Case Registered

Navi MumbaiNavi Mumbai Water Cut: Supply to Be Shut Down for 7 Hours in THESE Areas on January 7 — Check Timings

MumbaiMumbai Matrimonial Website Scam: Rs 200 Crore Fraud Racket Busted in Mira Road, 7 Arrested

MaharashtraBeed Shocker: 38-Year-Old Municipal Plumber Shot and Stabbed to Death in Ankush Nagar

Mumbai Realted Stories

MumbaiMumbai: Fire Breaks Out at Flat Near Daisy Shah's Bandra Residence; Actress Claims Crackers from BMC Elections 2026 Campaign Sparked Blaze (VIDEO)

MumbaiMNS Suffers Twin Blows in Mumbai: Leaders Join BJP and Shinde Sena, Party Rattled Ahead of BMC Polls

MumbaiSantosh Dhuri Slams Raj Thackeray After Joining BJP, Alleges MNS 'Surrendered' To Uddhav Sena

MumbaiMumbai Traffic Update: C. D. Barfiwala Road and Veera Desai Road to Remain Shut Amid Major Infrastructure Projects - Check Alternate Route and Other Details

MumbaiMumbai Temple Corridor Plan: Siddhivinayak Link Project Aims to Ease Pilgrim Movement Across Major Shrines