Mumbai: RTI Reveals BMC Fines Contractors Rs 35 Crores for Coastal Road Project Delays

By Amit Srivastava | Updated: August 5, 2024 17:30 IST

The Brihanmumbai Municipal Corporation (BMC) has imposed fines amounting to only Rs 35 crores on contractors for delays in ...

Open in App

The Brihanmumbai Municipal Corporation (BMC) has imposed fines amounting to only Rs 35 crores on contractors for delays in Mumbai’s Coastal Road Project. This information was revealed through a Right to Information (RTI) request by civic activist Anil Galgali. The ambitious Mumbai Coastal Road Project has missed its deadline, with no updates on a new deadline. In response to the RTI query, the BMC stated that fines totaling Rs 35 crores were imposed on the contractors due to project delays.

RTI activist Anil Galgali sought various details from the BMC regarding the Mumbai Coastal Road Project. The Coastal Road Project Department of the BMC informed Galgali that the project is divided into three parts: Under Part 1, the work from Priyadarshini Park to Baroda Palace has been awarded to M/s Larsen & Toubro. A fine of Rs 11.63 crores has been imposed. The original deadline for completing Part 1 was October 12, 2022. This work has been extended three times: June 9, 2023, September 10, 2023, and May 22, 2025.

Under Part 2, the work from Baroda Palace to the southern end of the Bandra Worli Sea Link has been awarded to M/s HCC-HDC. A fine of Rs 16.13 crores has been imposed. The original deadline for completing Part 2 was October 15, 2022. This work has been extended three times: October 6, 2023, October 7, 2023, and October 25, 2024.

Under Part 4, the work from Princess Street to Priyadarshini Park has been awarded to M/s Larsen & Toubro. A fine of Rs 7.25 crores has been imposed so far. The original deadline for completing Part 4 was October 12, 2022. This work has been extended three times: May 25, 2023, November 26, 2023, and April 2, 2024. Currently, 91% of the work has been completed, and the project is in its final stages. Larsen & Toubro sent a written request to the BMC on July 23, 2024, seeking an extension of 181 days, citing eight reasons for the extension.

According to Anil Galgali, the fines imposed are low compared to the increase in project costs. Contractors aim to secure ambitious projects like the Coastal Road but often fail to complete them on time, leading to increased costs. These additional expenses are ultimately covered by the taxes paid by ordinary Mumbaikars.

Tags: Coastal Road projectrtimumbaiContractors complaints departmentMaharashtra NewsBMC
Open in App

Related Stories

Navi MumbaiNavi Mumbai: 2-Day-Old Baby Found Abandoned Outside Orphanage; Parents Traced Within 24 Hours

PunePune Tragedy: 1 Dead, 3 Injured as Slab of Under-Construction Building Collapses in Camp Area

NagpurNagpur: RPF Constable Rescues Woman from Falling Under Moving Train at Railway Station (Watch Video)

MaharashtraDombivli MLA Ravindra Chavan Takes Charge as New Maharashtra BJP President, Replacing Chandrashekhar Bawankule

PunePune: Varandha Ghat Remains Closed Every Year Despite Repairs, Citizens Raise Questions

Mumbai Realted Stories

MumbaiMumbai: Over 10 International Schools Receive Threat Emails in 2 Months via Foreign VPNs; Probe Underway

MumbaiMumbai Horror: Father Allegedly Beats and Burns 5-Year-Old Daughter with Cigarette in Mankhurd; Arrested

MumbaiMumbai: YouTuber Arrested for Duping Youth Across India with False Promises of Jobs in Foreign Countries

PuneSwargate Rape Case: Pune Court Denies Bail to Accused Dattatray Gade

Mumbai'Saying I Love You Doesn’t Mean Desire for Sex': Bombay HC Acquits Man in 2015 Molestation Case