Chhatrapati Sambhajinagar: The Aurangabad Bench of Bombay High Court comprising Justice Ravindra Ghuge and Justice Y G Khobragade underlined ... ...
Lokmat News Network Aurangabad The work of the new pipeline from Jayakwadi dam to Aurangabad worth Rs 2,740 crore ... ...
Aurangabad: The road work of the cofferdam which will be developed in Jayakwadi dam was completed. The actual work ... ...
Aurangabad: The divisional commissioner Sunil Kendrekar, on Tuesday, ordered the contractor of the new water supply scheme, to complete ... ...
Aurangabad, Sept 16: The Aurangabad Municipal Corporation (AMC) municipal commissioner Abhijeet Chaudhari has underlined that 11 elevated storage reservoirs ... ...
Aurangabad, Aug 5: The new water supply scheme (of Rs 1680 crore) is likely to gain momentum as after ... ...
Lokmat News Network Aurangabad, July 7: The ambitious new water supply scheme valuing Rs 1680 crore which was sanctioned ... ...
Divisional Commissionerate recommends replacement of 700 mm pipeline with a 900 mm one Kendrekar pulls up AMC and MJP ... ...